Winter Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

The purpose of the Project Communications Management Knowledge Area is to:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Full Access
Question # 5

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Full Access
Question # 6

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Full Access
Question # 7

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Full Access
Question # 8

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Full Access
Question # 9

Which project document is updated in the Control Stakeholder Engagement process?

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Full Access
Question # 10

Outputs of the Control Communications process include:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Full Access
Question # 11

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Full Access
Question # 12

Success is measured by benefits realization for a:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Full Access
Question # 13

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Full Access
Question # 14

Which stakeholder approves a project's result?

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Full Access
Question # 15

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

A.

improvement

B.

program

C.

result

D.

portfolio

Full Access
Question # 16

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Full Access
Question # 17

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Full Access
Question # 18

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Full Access
Question # 19

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Question # 20

Whose approval may be required for change requests after change control board (CCB) approval?

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Full Access
Question # 21

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Full Access
Question # 22

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Full Access
Question # 23

Perform Integrated Change Control is the process of:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Full Access
Question # 24

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Full Access
Question # 25

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Full Access
Question # 26

A disadvantage associated with virtual teams is that they:

A.

Require communication technology that is not readily available.

B.

Create difficulties when including people with disabilities.

C.

Often cannot accommodate teams that work different hours or shifts.

D.

Create the possibility for misunderstandings to arise.

Full Access
Question # 27

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

Full Access
Question # 28

Which element does a project charter contain?

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Full Access
Question # 29

A graphic display of project team members and their reporting relationships is known as a:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Full Access
Question # 30

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Full Access
Question # 31

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Full Access
Question # 32

Assigned risk ratings are based upon:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders' tolerances.

Full Access
Question # 33

When can pre-assignment of project team members occur?

A.

When the project uses capital expenditures

B.

When the required staff can be acquired from outside sources

C.

When the project would be ignored due to travel expenses

D.

When the project is the result of specific people being promised as part of a competitive proposal

Full Access
Question # 34

Which process is included in the Project Integration Management Knowledge Area?

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Full Access
Question # 35

Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Full Access
Question # 36

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Full Access
Question # 37

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Full Access
Question # 38

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Full Access
Question # 39

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Full Access
Question # 40

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Full Access
Question # 41

An input to the Create WBS process is a:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Full Access
Question # 42

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Full Access
Question # 43

Portfolio Management is management of:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Full Access
Question # 44

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Full Access
Question # 45

The scope management plan is a subsidiary of which project document?

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Full Access
Question # 46

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Full Access
Question # 47

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Full Access
Question # 48

During which process group is the quality policy determined?

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Full Access
Question # 49

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Full Access
Question # 50

Which organizational process assets update is performed during the Close Procurements process?

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Full Access
Question # 51

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Full Access
Question # 52

The stakeholder register is an output of:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Full Access
Question # 53

A project management office manages a number of aspects including the:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Full Access
Question # 54

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Full Access
Question # 55

Which of the following is contained within the communications management plan?

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Full Access
Question # 56

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Full Access
Question # 57

Specification of both the deliverables and the processes is the focus of:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Full Access
Question # 58

What is the definition of Direct and Manage Project Execution?

A.

Integrating all planned activities

B.

Performing the activities included in the plan

C.

Developing and maintaining the plan

D.

Execution of deliverables

Full Access
Question # 59

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Full Access
Question # 60

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Full Access
Question # 61

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Full Access
Question # 62

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Full Access
Question # 63

Cost baseline is an output of which of the following processes?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Estimate Activity Resources

Full Access
Question # 64

Which of the following investigates the likelihood that each specific risk will occur?

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Full Access
Question # 65

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Full Access
Question # 66

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Full Access
Question # 67

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Full Access
Question # 68

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Full Access
Question # 69

The product scope description is used to:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Full Access
Question # 70

What is the total float of the critical path?

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Full Access
Question # 71

The Verify Scope process is primarily concerned with:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Full Access
Question # 72

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Full Access
Question # 73

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Full Access
Question # 74

Which of the following is an input to Direct and Manage Project Execution?

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Full Access
Question # 75

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Full Access
Question # 76

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Full Access
Question # 77

Which of the following statements correctly characterizes pull communication?

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Full Access
Question # 78

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

Full Access
Question # 79

The procurement process that documents agreements and related documentation for future reference is known as:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Full Access
Question # 80

Which of the following processes are part of the Project Integration Management Knowledge Area?

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Full Access
Question # 81

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Full Access
Question # 82

In which Process Group are lessons learned documented?

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Full Access
Question # 83

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Full Access
Question # 84

During which process would stakeholders provide formal acceptance of the completed project scope?

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Full Access
Question # 85

Documented identification of a flaw in a project component together with a recommendation is termed a:

A.

corrective action.

B.

preventive action.

C.

non-conformance report,

D.

defect repair.

Full Access
Question # 86

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Full Access
Question # 87

The process of identifying the stakeholders' information needs is completed during:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Full Access
Question # 88

Managing procurement relationships and monitoring contract performance are part of which process?

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Full Access
Question # 89

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

A.

There is a cost underrun.

B.

There is a cost overrun.

C.

The project may not meet the deadline.

D.

The project is 20 days behind schedule.

Full Access
Question # 90

"Tailoring" is defined as the:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Full Access
Question # 91

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Full Access
Question # 92

What is the most accurate rough order of magnitude (ROM)?

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Full Access
Question # 93

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Full Access
Question # 94

Which process involves identifying and documenting the logical relationships between project activities?

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Full Access
Question # 95

Which of the following is a tool or technique of the Define Activities process?

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Full Access
Question # 96

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Full Access
Question # 97

Which process determines the risks that might affect the project?

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Full Access
Question # 98

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Full Access
Question # 99

What is a tool to improve team performance?

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Full Access
Question # 100

Which of the following strategic considerations often results in project authorization?

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

Full Access
Question # 101

Which type of risk diagram is useful for showing time ordering of events?

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Full Access
Question # 102

Which can be used to determine whether a process is stable or has predictable performance?

A.

Matrix diagram

B.

Histogram

C.

Control chart

D.

Flowchart

Full Access
Question # 103

What is the primary benefit of meeting quality requirements?

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Full Access
Question # 104

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Full Access
Question # 105

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Full Access
Question # 106

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

Full Access
Question # 107

Which type of chart is a graphic representation of a process showing the relationships among process steps?

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Full Access
Question # 108

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Full Access
Question # 109

Which of the following is an example of the simplest fixed-price contract?

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Full Access
Question # 110

Which tool or technique is used in Manage Stakeholder Expectations?

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests

Full Access
Question # 111

In which Project Management Process Group is the project charter developed?

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Full Access
Question # 112

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Full Access
Question # 113

Which of the following factors is lowest at the start of the project?

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Full Access
Question # 114

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Full Access
Question # 115

Which of the following is an input to Control Scope?

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Full Access
Question # 116

Quality metrics are an output of which process?

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Full Access
Question # 117

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Full Access
Question # 118

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Full Access
Question # 119

Which of the following is an output of the Distribute Information process?

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Full Access
Question # 120

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Full Access
Question # 121

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Full Access
Question # 122

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

A.

Portfolio

B.

Process

C.

Project

D.

Program

Full Access
Question # 123

Which of the following is an example of schedule compression?

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Full Access
Question # 124

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Full Access
Question # 125

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Full Access
Question # 126

Which of the following are outputs of Develop Project Team?

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Full Access
Question # 127

In which process might a project manager use risk reassessment as a tool and technique?

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Full Access
Question # 128

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Full Access
Question # 129

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Full Access
Question # 130

Which tool or technique is used in Close Procurements?

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Full Access
Question # 131

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.

100

B.

120

C.

1,000

D.

1,200

Full Access
Question # 132

The following is a network diagram for a project.

The free float for Activity E is how many days?

A.

2

B.

3

C.

5

D.

8

Full Access
Question # 133

The scope management plan and scope baseline are contained in:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Full Access
Question # 134

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Full Access
Question # 135

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Full Access
Question # 136

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Full Access
Question # 137

During which process does the project team receive bids and proposals?

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Full Access
Question # 138

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Full Access
Question # 139

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Full Access
Question # 140

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

16

Full Access
Question # 141

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 142

For a stakeholder with low interest and high power, the project manager should:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Full Access
Question # 143

Project Stakeholder Management focuses on:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Full Access
Question # 144

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Full Access
Question # 145

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Question # 146

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Full Access
Question # 147

Which enterprise environmental factors may influence Plan Schedule Management?

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Full Access
Question # 148

Which kind of communication should the project manager use when creating reports for government bodies?

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Full Access
Question # 149

What estimating technique is used when there is limited information?

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Full Access
Question # 150

In the Control Quality process, which tools and techniques techniques can be applied to verify deliverable?

A.

Statistical sampling, inspection, and meetings

B.

Lessons learned register, control charts, and product evaluation

C.

Checklists, retrospective documents, and approved change requests

D.

Black box tests, questionnaires and surveys, and lessons learned register

Full Access
Question # 151

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

A.

Appraisal costs

B.

Management reserves

C.

Cost of nonconformance

D.

Cost of conformance

Full Access
Question # 152

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

A.

2

B.

3

C.

4

D.

6

Full Access
Question # 153

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

A.

Matrix - strong

B.

Matrix - balanced

C.

Virtual

D.

Functional

Full Access
Question # 154

What kind of skills should a project manager use when attempting to achieve consensus by balancing the conflicting and competing goals of project stakeholders?

A.

Interpersonal skills and the ability to manage people

B.

Strategic and business management skills

C.

Technical and business management skills

D.

Business analysis skills and expertise

Full Access
Question # 155

To ensure stakeholder satisfaction; identified stakeholder needs should all be

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Full Access
Question # 156

What important qualities should project managers possess for strategic and business management?

A.

Skills and behaviors related to specific domains of project management

B.

Knowledge and competencies needed to guide and motivate a team

C.

Skills and behaviors needed to help an organization achieve its goals

D.

Expertise in the industry and organization that deliver better outcomes

Full Access
Question # 157

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Full Access
Question # 158

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

Full Access
Question # 159

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Full Access
Question # 160

Which of the following are components of the project management plan?

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

Full Access
Question # 161

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

A.

Resource availability

B.

Infrastructure

C.

Academic research

D.

Corporate knowledge base

Full Access
Question # 162

Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?

A.

Conduct Procurements

B Plan Procurement Management

B.

Plan Risk Responses

C.

Plan Risk Management

Full Access
Question # 163

Select three elements that apply to agile/ adaptive environments

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

Full Access
Question # 164

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Full Access
Question # 165

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

A.

Sensitivity analysis

B.

Monte Carlo analysis

C.

Expected monetary value analysis

D.

Decision tree analysis

Full Access
Question # 166

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Full Access
Question # 167

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Full Access
Question # 168

Which of the following is an example of tacit knowledge

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Full Access
Question # 169

What tools or techniques are necessary to create the project management plan?

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Full Access
Question # 170

What tool or technique is used in the Collect Requirements process?

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Full Access
Question # 171

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Full Access
Question # 172

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Full Access
Question # 173

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Full Access
Question # 174

Which is the appropriate tool to identify the possible correlation two elements in aprocess?

A.

Scatter diagram

B.

Cause and effect diagram

C.

Histogram

D.

Control charts

Full Access
Question # 175

What are the two most common contract types used in a project?

A.

Cost plus award fee (CPAF) contract and fixed price contract

B.

Fixed price contract and cost-reimbursable contract

C.

Cost-reimbursable contract and time and material (T&M) contract

D.

Time and material (T&M) contract and cost plus award fee (CPAF) contract

Full Access
Question # 176

What do top project managers do to maximize their sphere of influence within a project team?

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project's viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Full Access
Question # 177

What tool or technique is primarily used to plan risk responses'?

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Full Access
Question # 178

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

A.

Stakeholder engagement plan and organizational process assets

B.

Project schedule and stakeholder register

C.

Quality management plan and risk register

D.

Basis of estimates and scope baseline

Full Access
Question # 179

Which enterprise environmental factors should be considered when creating a new procurement contract?

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Full Access
Question # 180

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Full Access
Question # 181

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Full Access
Question # 182

What is purpose of using the building information model (BIM) in software tools in the construction field?

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Full Access
Question # 183

What is the process of ensuring that project resources are assigned and available?

A.

Control Procurements

B.

Acquire Resources

C.

Control Resources

D.

Plan Procurement Management

Full Access
Question # 184

Which can be used to convert a verified deliverable to an accepted deliverable?

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

Full Access
Question # 185

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.

B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge

C.

An iterative scheduling and on-demand, pull-based scheduling will be required.

D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted

Full Access
Question # 186

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Full Access
Question # 187

A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?

A.

Collaborate/Problem Solve

B.

Compromise/Reconcile

C.

Smooth/Accommodate

D.

Withdraw/Avoid

Full Access
Question # 188

Which of the following set of items belongs to the communications management plan?

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Full Access
Question # 189

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Full Access
Question # 190

In which project risk management process is the data analysis technique not used?

A.

Plan Risk Management

B.

Implement Risk Response

C.

Monitor Risks

D.

Perform Quantitative Risk Analysis

Full Access
Question # 191

What is an emerging practice in stakeholder engagement?

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Full Access
Question # 192

A project team member identifies a possibility......the team member's idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member's idea?

A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.

B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.

C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.

D.

Submit the idea as a change request to the change control board to ensure that all interests are met.

Full Access
Question # 193

What is the main purpose of Project Quality Management?

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Full Access
Question # 194

What purpose does the hierarchical focus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the focus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Full Access
Question # 195

What is the most important skill that project managers should possess to lead stakeholders throughout a project?

A.

Communication

B.

Problem-solving

C.

Negotiating

D.

Trust-building

Full Access
Question # 196

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

A.

Traceability matrix

B Lessons learned

B.

Change control procedures

D Resource availability

Full Access
Question # 197

An input to Close Project or Phase is:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Full Access
Question # 198

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Full Access
Question # 199

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$175

Full Access
Question # 200

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Full Access
Question # 201

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Full Access
Question # 202

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Full Access
Question # 203

An input used in developing the communications management plan is:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Full Access
Question # 204

Stakeholder satisfaction should be managed as a key project:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Full Access
Question # 205

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Full Access
Question # 206

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 207

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Full Access
Question # 208

A temporary endeavor that creates a unique product or service is called a:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

Full Access
Question # 209

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Full Access
Question # 210

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Full Access
Question # 211

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Full Access
Question # 212

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Full Access
Question # 213

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Full Access
Question # 214

A project manager should document the escalation path for unresolved project risks in the:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Full Access
Question # 215

Which document describes the necessary information to determine if a project is worth the required investment?

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Full Access
Question # 216

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

Full Access
Question # 217

The Monitoring and Controlling Process Group includes processes that:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Full Access
Question # 218

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A.

Negative

B.

Zero

C.

Positive

D.

Free

Full Access
Question # 219

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Full Access
Question # 220

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Full Access
Question # 221

Which item is a formal proposal to modify any document, deliverable, or baseline?

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Full Access
Question # 222

Which item is an input to the Define Activities process?

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Full Access
Question # 223

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

Full Access
Question # 224

Inputs to the Plan Schedule Management process include:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Full Access
Question # 225

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Full Access
Question # 226

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Full Access
Question # 227

Identify Risks is part of which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 228

The number of potential communication channels for a project with 5 stakeholders is:

A.

10.

B.

12.

C.

20.

D.

24.

Full Access
Question # 229

Which tool or technique is used in the Plan Scope Management process?

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Full Access
Question # 230

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Full Access
Question # 231

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

A.

smooth/accommodate.

B.

force/direct,

C.

collaborate/problem solve,

D.

compromise/reconcile.

Full Access
Question # 232

Change requests are processed for review and disposition according to which process?

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Full Access
Question # 233

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Full Access
Question # 234

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Full Access
Question # 235

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Full Access
Question # 236

An example of a group decision-ma king technique is:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Full Access
Question # 237

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Full Access
Question # 238

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Full Access
Question # 239

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

Full Access
Question # 240

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Full Access
Question # 241

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Full Access
Question # 242

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Full Access
Question # 243

The Plan Stakeholder Management process belongs to which Process Group?

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Full Access
Question # 244

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Full Access
Question # 245

A tool or technique used in the Control Procurements process is:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Full Access
Question # 246

What are the objectives of Initiation processes?

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Full Access
Question # 247

What purpose does the hierarchical locus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Full Access
Question # 248

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Full Access
Question # 249

It you established a contingency reserve including time, money, and resources, how are you handling risk?

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Full Access
Question # 250

Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Organizational breakdown structure (OBS)

D.

Resource breakdown structure (RBS)

Full Access
Question # 251

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Full Access
Question # 252

The Agile principle "welcome changing requirement, even late in development" relates to which agile manifesto?

A.

Working software over comprehensive documentation

B.

Individuals and interactions over processes and tools

C.

Customer collaboration over contract negotiation

D.

Responding to change over following a plan

Full Access
Question # 253

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

A.

Prompt lists and data analysis

B.

Reports and representations of uncertainty

C.

Data analysis and risk audits

D.

Interpersonal and team skills and project management Information system

Full Access
Question # 254

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Full Access
Question # 255

Which of these is true of project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Full Access
Question # 256

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

A.

Hold a face-to-face meeting with the project manager and warn them.

B.

Point the director to a link where they can take a look at the reports.

C.

Invite stakeholders to attend monthly progress review meetings.

D.

Ask the project manager to update the monthly status report distribution list.

Full Access
Question # 257

The features and functions that characterize a result, product, or service can refer to:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

Full Access
Question # 258

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Full Access
Question # 259

What is the difference between quality metrics and quality measurements?

A.

Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process

B.

Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes

C.

Quality metrics and measurements are the same concept

D.

Quality metrics is the general objective and the measurements are the specific objectives

Full Access
Question # 260

When managing costs in an agile environment, what should a project manager consider?

A.

Lightweight estimation methods can be used as changes arise.

B.

Agile environments make cost aggregation more difficult.

C.

Agile environments make projects more costly and uncertain.

D.

Detailed cost calculations benefit from frequent changes.

Full Access
Question # 261

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Full Access
Question # 262

What is a tailoring consideration for the application of Project Risk Management processes?

A.

Project complexity

B.

Procurement criteria

C.

Communication technology

D.

Knowledge management

Full Access
Question # 263

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Full Access
Question # 264

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Full Access
Question # 265

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements

Full Access
Question # 266

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Acquire Resources

Full Access
Question # 267

The primary purpose of the stakeholder register is to:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Full Access
Question # 268

What are the key tools for managing project knowledge?

A.

Expert judgment and data gathering

B.

Networking and storytelling

C.

Data analysis and decision making

D.

Prototypes and product analysis

Full Access
Question # 269

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Full Access
Question # 270

What organizational asset can influence the Plan Risk Management process?

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Full Access
Question # 271

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

A.

Project level

B.

Organizational level

C.

Industry level

D.

Influential level

Full Access
Question # 272

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Full Access
Question # 273

What tool or technique can improve a products final characteristics?

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Full Access
Question # 274

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Full Access
Question # 275

What scenario describes when a project must be created due to market demand?

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Full Access
Question # 276

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

A.

Project activities

B.

Work packages

C.

Planning packages

D.

Project deliverables

Full Access
Question # 277

In which Project Cost Management process is work performance data included?

A.

Plan Cost Management

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Question # 278

Which is an example of analogous estimating?

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Full Access
Question # 279

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

A.

USS-30,000

B.

US$120,000

C.

US$370,000

D.

US$400,000

Full Access
Question # 280

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

Full Access
Question # 281

What are the inputs of the Estimate Costs process?

A.

Project management plan, work performance data, enterprise environmental factors, and organizational process assets

B.

Project management plan, project documents, enterprise environmental factors, and organizational process assets

C.

Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets

D.

Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Full Access
Question # 282

Which of the following are processes associated with Project Cost Management?

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs

Full Access
Question # 283

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Full Access
Question # 284

Which conflict resolution technique produces the most lasting results?

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Full Access
Question # 285

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Full Access
Question # 286

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

A.

Identify Stakeholders

B.

Plan Stakeholder Engagement

C.

Manage Stakeholder Engagement

D.

Monitor Slakeholder Engagement

Full Access
Question # 287

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Full Access
Question # 288

What can increase the complexity of the Manage Stakeholder Engagement process?

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Full Access
Question # 289

What is the difference between verified and accepted deliverables?

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Full Access
Question # 290

Which are examples of processes that may be used once or at predefined points in the project life cycle?

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Full Access
Question # 291

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

A.

Create Work Breakdown Structure (WBS)

B.

Create Scope Baseline

C.

Collect Requirements

D.

Define Scope

Full Access
Question # 292

A project manager Is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?

A.

Monitor Stakeholder Engagement

B.

Monitor Communications

C.

Manage Communications

D.

Manage Stakeholder Engagement

Full Access
Question # 293

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

A.

Work performance information

B.

Bidder conferences

C.

Complexity of procurement

D.

Procurement management plan

Full Access
Question # 294

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Full Access
Question # 295

During project selection, which factor is most important?

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Full Access
Question # 296

The staffing management plan is part of the:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Full Access
Question # 297

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Full Access
Question # 298

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Full Access
Question # 299

Which of the following is a tool or technique used in the Acquire Project Team process?

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Full Access
Question # 300

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Full Access
Question # 301

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Full Access
Question # 302

A tool and technique used during the Collect Requirements process is:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Full Access
Question # 303

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Full Access
Question # 304

Funding limit reconciliation is a tool and technique used in which process?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Full Access
Question # 305

Which is an output of the Collect Requirements process?

A.

Requirements traceability matrix

B.

Project scope statement

C.

WBS dictionary

D.

Work performance measurements

Full Access
Question # 306

The correct equation for schedule variance (SV) is earned value:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Full Access
Question # 307

The initial development of a Project Scope Management plan uses which technique?

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

Full Access
Question # 308

An input to the Estimate Activity Resources process is:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Full Access
Question # 309

Which of the following is an output of Close Procurements?

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Full Access
Question # 310

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Full Access
Question # 311

Which activity may occur at project or phase closure?

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

Full Access
Question # 312

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Full Access
Question # 313

Which of the following is a group decision-making technique?

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Full Access
Question # 314

Which quality control technique illustrates the 80/20 principle?

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Full Access
Question # 315

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Full Access
Question # 316

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Full Access
Question # 317

The completion of the project scope is measured against the:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Full Access
Question # 318

Projects are separated into phases or subprojects; these phases include:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Full Access
Question # 319

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Full Access
Question # 320

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Full Access
Question # 321

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Full Access
Question # 322

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Full Access
Question # 323

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Full Access
Question # 324

Which characteristics do effective project managers possess?

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Full Access
Question # 325

Which of the following is a project constraint?

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Full Access
Question # 326

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Full Access
Question # 327

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Full Access
Question # 328

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

Full Access
Question # 329

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Full Access
Question # 330

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 331

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Full Access
Question # 332

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Full Access
Question # 333

Resource calendars are included in the:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Full Access
Question # 334

At the end of the project, what will be the value of SV?

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Full Access
Question # 335

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Full Access
Question # 336

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

Full Access
Question # 337

Prototype development may be used as a tool for which of the following risk response strategies?

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Full Access
Question # 338

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Full Access
Question # 339

The risk shared between the buyer and seller is determined by the:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Full Access
Question # 340

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Full Access