Weekend Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Full Access
Question # 5

A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution.

What should the project leader do?

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Full Access
Question # 6

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Full Access
Question # 7

Following an upgrade, a software support team is overwhelmed by the number of tickets being submitted by end users. The team's manager is pushing the team to "work smart" by focusing on activities that deliver the most value in the least amount of time.

What should the team do?

A.

Work longer hours to complete more of the support backlog.

B.

Work support tickets in the order in which they were received.

C.

Place tickets on hold until the team completes an analysis of the backlog to identify and resolve systemic issues.

D.

Add members to the support team.

Full Access
Question # 8

What is the first thing an agile development team should do when planning an iteration?

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Full Access
Question # 9

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Full Access
Question # 10

During a daily stand up meeting, a developer expresses concerns that the selected technology limits the number of concurrent users. What should the agile team lead do?

A.

Ask the team to conduct research to find a viable solution.

B.

Select a better technology for team implementation.

C.

Obtain customer input on their technology requirements.

D.

Consult the product owner about their non-functional requirements.

Full Access
Question # 11

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

A.

Influence the customer

B.

Mention the idea at the next retrospective

C.

Show the customer how much time and money would be saved

D.

Present the idea at the next ceremony attended by stakeholders to obtain their input

Full Access
Question # 12

How should an agile project leader interact with the product owner?

A.

Conduct regular one-on-one meetings to review development features and trace them back to the product roadmap.

B.

Ensure that they attend regular sprint meetings to provide product-feature feedback.

C.

Share any new versions of the project plan with them, including updated statuses for tasks and project milestones.

D.

Schedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints.

Full Access
Question # 13

A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals. What should the scrum master mention at the next retrospective?

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Full Access
Question # 14

What should the agile practitioner know about tracking velocity?

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Full Access
Question # 15

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.

What should the team do?

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Full Access
Question # 16

A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?

A.

Obtain executive team buy-in by conducting a meeting to present the advantages of agile principles and processes.

B.

Issue a memo of understanding that agile principles should be implemented for all new projects.

C.

Introduce agile principles and processes, then make the change an experiment to obtain buy-in.

D.

Require all staff and management to attend agile training and adhere to its principles.

Full Access
Question # 17

During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends the discussion. This causes a team member to withdraw from future collaboration.

How could the project leader have avoided this?

A.

Led by example by encouraging the team to engage in consensus-driven decision making

B.

Iterated the need for agile teams to make quick decisions, then followed up with that team member

C.

Empowered a team member to facilitate decision making then made a final decision on behalf of the team

D.

Refrained from participating in the team's decision-making process, except to document and communicate results

Full Access
Question # 18

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Full Access
Question # 19

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release.

What should the agile coach do?

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Full Access
Question # 20

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.

What should be proposed to the team?

A.

Have other team developers attend training to learn database skills.

B.

Monitor the retrospectives of two additional sprints before taking action.

C.

Plan fewer stories for the sprint to reduce the database engineers' workload.

D.

Ask the scrum master to work with the product owner to remove backlog stories that have database dependency.

Full Access
Question # 21

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

A.

Advise the product owner that the story will have to wait until the next sprint.

B.

Work extra hours to complete the story and satisfy the customer's requirements.

C.

Break down the story into smaller increments and negotiate other stories on the sprint backlog.

D.

Increase the length of the sprint to accommodate the story.

Full Access
Question # 22

Stakeholders are displeased with the latest release of a product's software While most stakeholders attended every sprint review they were otherwise largely uninvolved in the project.

What should the agile practitioner have done to ensure stakeholder satisfaction?

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Full Access
Question # 23

An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" - a story-telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.

What is the project leader trying to create?

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other's weaknesses and strengths.

Full Access
Question # 24

The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

A.

Commit to a specific feature set for delivery.

B.

Explain that a commitment will be provided after planning.

C.

Have the team estimate in story points to commit to a specific set of features.

D.

Use the team's historical velocity to calculate a range of features that can be delivered.

Full Access
Question # 25

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Full Access
Question # 26

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Full Access
Question # 27

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

A.

Invited end customers to attend the stand ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Full Access
Question # 28

During planning for the next iteration an agile team identifies most of the story points that are expected to be delivered How should an agile practitioner work with the team to help identify the iteration's remaining scope?

A.

Convince the team to stop planning and keep the size small

B.

Identify the technically minimal and achievable tasks

C.

Refer to the remaining prioritized backlog items

D.

Select some of the smallest items from the backlog

Full Access
Question # 29

A project team realizes that an important task on the iteration backlog will take more time than originally estimated What should the project team do?

A.

Continue working on the task until it is completed

B.

Remove the task owner from the project team

C.

Add resources to reduce time to task completion

D.

Stop working on the task and include it in the next iteration

Full Access
Question # 30

A team identifies the number of threats and lists them in the order in which they were identified. After analyzing a cause-and-effect diagram, the ownership of the threats and their treatment is assigned, and a number of risk cards are placed on the Kanban board.

What approach should be used to manage these threats?

A.

Create a risk register detailing the threats, their causes, and their treatment strategies; and complete ownership to provide tighter risk control and a stakeholder communication tool.

B.

Focus on the threats during the daily stand up and ensure they are visible to the entire team and other interested parties.

C.

Prioritize the risks based on their criticality and timing, and track actions to closure.

D.

Ensure that the prioritization of threats is complete, and that ownership actions are assigned and visible to everyone.

Full Access
Question # 31

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing it's teams.

What strategy should be employed to re-organize the teams?

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption and

capitalize on synergies

C.

After grouping individuals by role multi-discipline teams should be created that are comprised of one member from each

role

D.

Features should be prioritized and then teams should be organized around those priorities

Full Access
Question # 32

A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.

What should the product owner do?

A.

Determine the required tasks for implementing the high-level features

B.

Identify the detailed design for the high-level features

C.

Prioritize the product backlog for the upcoming release.

D.

Estimate the user stories in the iteration backlog

Full Access