In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?
A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.
Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that
those issues are resolved?
The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.
Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?
Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
The document that defines the process for managing requirements revisions is the:
Which tool should be used to improve the communication of product needs with the stakeholders and to improve their understanding?
The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.
What could have caused this issue?
The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?
A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification. What is the best action to take to ensure the design meets customer requirements?
Which of the following techniques is used to identify ambiguous or unverifiable requirements?
Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.
Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?
After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides
enough information to check if the requirement has been met.
Which of the following would work best in this case?
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?
A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.
Which of the following techniques would the business analyst use to identify stakeholders?
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?
A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.
How would the business analyst define the scope of this project?
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred ”
What could have prevented the stakeholder from being surprised about the status change?
A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.
Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?
Which technique or tool is used to obtain acceptance of the delivered product?
Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?
An insurance company embarks on a project to replace its current enrollment and billing software application, which will no longer be supported by the end of the calendar year. The new enrollment and billing application must be implemented before the current vendor contract ends. The business analyst gathers the initial requirements for the new enrollment and billing application. Based on the large
volume of requirements, the business analyst realizes that the requirements will need to be prioritized.
Which requirements prioritization method should the business analyst use for this project?
A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.
Which of the following documents should be used?
A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.
What step should the business analyst take next?
The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.
Which decision role was used?
A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.
What should the business analyst do next?
The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?
One of the main purposes for creating a requirements traceability matrix is to:
The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?
The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.
Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid
recommendation?
An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.
Which approach will better cope with the requirements’ volatility?
How should a business analyst determine whether a solution satisfies business requirements?
A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.
Which model should the team employ to ensure the most effective representation of analysis boundary?
A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.
What is the purpose of this meeting?
When managing a product backlog, which statement best describes how to determine the value of backlog items?
In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.
Which technique could have prevented this problem from occurring?
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.
How can the business analyst determine how well the solution meets the business case?
The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?
A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation
process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume
reporting required by the company's financial department. The business analyst for the project determines that the selection criteria
needed was not specified in the system requirements or design specifications.
Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement
was missed?
A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.
Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?
A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)
versioning?
After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?
Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?