Weekend Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

Once an Epic is approved, an Epic Owner tracks the Epic through implementation.

A.

True

B.

False

Full Access
Question # 5

(Select 3) What primary roles are most responsible for ensuring successful execution at the Value Stream Level?

A.

Solution Management

B.

Value Stream Engineer

C.

Solution Architect/Engineer

D.

Customer

E.

Release Management

Full Access
Question # 6

(Select 2) What are the right scenarios for using SAFe Foundations Training Materials?

A.

Train Scrum Masters in servant leadership following "SAFe for Teams" training.

B.

Make an initial presentation on SAFe to the organization.

C.

Familiarize Release Train Engineers with the PI Planning process.

D.

Familiarize executives with SAFe.

E.

Train the teams prior to PI Planning.

Full Access
Question # 7

Capabilities are similar to Features and can be managed in the Program Backlog.

A.

True

B.

False

Full Access
Question # 8

(Select 3) You are invited to help a program where, even though not mandated by the external environment, management requires teams to make big, up-front, and detailed scope commitments for every release.

What would you do to best coach the decision-makers?

A.

Illustrate the power of feedback in content decision-making.

B.

Emphasize the value of "Responding to change" from the Agile Manifesto.

C.

Explain that too much up-front detail demotivates Product Owners as they have almost nothing to do thereafter.

D.

Explain the "understand and exploit variability" principle or product development flow.

E.

Explain why development doesn't need to commit to anything in Agile.

Full Access
Question # 9

What is the target percentage for the Program Predictability Measure?

A.

<50%

B.

50-75%

C.

80-100%

D.

100%

E.

None of the above.

Full Access
Question # 10

ARTs that consist only of Feature teams do not require an Architectural Runway.

A.

True

B.

False

Full Access
Question # 11

If all Agile Release Trains in a Value Stream are organized around Capabilities, they don't require cross-train coordination.

A.

True

B.

False

Full Access
Question # 12

AFe assumes that programs commit to the key priorities within the current PI and provide a forecast for a few subsequent PIs.

A.

True

B.

False

Full Access
Question # 13

What concept is NOT on of the Core Value of SAFe?

A.

Predictability

B.

Alignment

C.

Transparency

D.

Built-in Quality

E.

Program execution

Full Access
Question # 14

(Select 2) What factors favor centralized decision-making?

A.

Infrequent decisions.

B.

Need for fast decision-making.

C.

Economies of scale

D.

Appropriate authority level of the decision maker.

E.

High cost of delay

Full Access
Question # 15

What is the primary purpose of the management meeting at the end of Day 1 of PI Planning?

A.

To assign business value to the teams' draft PI Objectives.

B.

To make adjustments to the PI scope and address program challenges.

C.

To design the next generation of the product.

D.

To evaluate the performance of teams.

Full Access
Question # 16

What is NOT a SAFE-recommended Metric?

A.

Number of lines of code produced.

B.

Number of new test cases automated.

C.

Number of test cases produced.

D.

Percent of unit test coverage.

E.

Percent of user stories accepted by the Product Owner.

F.

Number of defects outstanding.

Full Access
Question # 17

What does the SAFe budgeting model suggest?

A.

Each Strategic Theme receives a budget allocation when Strategic Themes span portfolios.

B.

Epics, Features, and Stories are funded based on their size in normalized Story points, while teams are allocated to high-priority work as needed.

C.

Each Value Stream receives budget allocation as a whole; individual work is not specifically budgeted.

D.

Each team gets budget allocation and Features are funded according to their size in normalized Story points.

Full Access
Question # 18

Iteration Goals have business value assigned by the Product Owner.

A.

True

B.

False

Full Access
Question # 19

(Select 3) How do you demo a spike?

A.

Spikes are strictly for internal learning of the team and do not need to be demoed.

B.

Showing the functioning code in the production environment.

C.

Showing the knowledge gained by the spike.

D.

Showing a prototype produced for the spike.

E.

Showing the quantitative data that will prove useful in developing future user stories.

Full Access
Question # 20

What are stretch objectives?

A.

Objectives that are beyond the capacity of the team and so are uncommitted for the PI.

B.

Objectives that are part of the team's capacity but not necessarily achievable during the PI.

C.

Objectives that are identified during the PI.

D.

Objectives that the business has promised to their Customers.

Full Access
Question # 21

(select 3) What are the 3 primary outputs of PI Planning?

A.

Program board

B.

Team PI Objectives

C.

Top 10 Features

D.

Vote of confidence/commitment

E.

Portfolio Vision

F.

Iteration Goals

Full Access
Question # 22

When is the Solution Demo conducted?

A.

On demand.

B.

At the end of each Sprint.

C.

At the end of each PI.

D.

Mid-PI.

Full Access
Question # 23

(Select 2) What are the 2 biggest reasons to reduce batch size?

A.

Make it easier to assess the state of smaller batches.

B.

Decrease stress on the system.

C.

Increase throughput.

D.

Produce less measurement overhead.

E.

Increase delivery reliability.

Full Access
Question # 24

(select 3) What does relentless improvement, as defined in SAFe, include?

A.

Hold people accountable.

B.

Hold employee reviews to provide fast feedback.

C.

Optimize the whole.

D.

Apply Lean problem-solving tools and techniques.

E.

Reflect at key Milestones.

Full Access
Question # 25

How does a team calculate its initial velocity during its first PI Planning meeting when teams don't have historic data?

A.

Assign 8 points per team member (not counting the Scrum Master and Product Owner) and subtract 1 point for each holiday or vacation day.

B.

It is not recommended to calculate velocity until the team has completed its first PI.

C.

Allow teams to establish their own velocity and then roll them up to calculate the velocity of the train.

D.

Assign 10 points per team member (not counting the Scrum Master and Product Owner) and subtract 1 point for each holiday or vacation day.

Full Access
Question # 26

Backlog items in an Expedite class of service can break WIP limits.

A.

True

B.

False

Full Access
Question # 27

Select 2) You are prioritizing Epics and the group cannot reach a consensus on WSJF parameters. What would be the best course of action to reduce inconsistencies?

A.

Collect additional input from other stakeholders.

B.

Take time to provide more detailed specifications for each Epic.

C.

Use strategic themes to help the group understand how an Epic contributes to the realization of the enterprise business strategy.

D.

Change the scale for WSJF parameters.

E.

Split Epics into Capabilities, prioritize them, and combine those priorities back to the Epic level.

Full Access
Question # 28

Typically, SAFe prioritizes Capabilities based on which of the following?

A.

Business value

B.

CoD (Cost of Delay)

C.

WSJF (Weighted Shortest Job First)

D.

Capacity allocation according to budget

Full Access
Question # 29

(Select 2) What factors foster team "Ba"?

A.

Decentralized decision-making.

B.

Built-in instability.

C.

Use of Feature Teams.

D.

Dunbar's number

Full Access
Question # 30

(Select 3) How do you demo a spike?

A.

Spikes are strictly for internal learning of the team and do not need to be demoed.

B.

Showing the functioning code in the production environment.

C.

Showing the knowledge gained by the spike.

D.

Showing a prototype produced for the spike.

E.

Showing the quantitative data that will prove useful in developing future user stories.

Full Access
Question # 31

(Select 3) Who is typically involved in the ART Sync?

A.

Scrum Masters

B.

Product Owners

C.

Business Owners

D.

Release Train Engineer

E.

Release Management

F.

Solution Management

Full Access
Question # 32

A Program Epic that originates from a Portfolio Epic takes precedence over all local priorities on that train.

A.

True

B.

False

Full Access
Question # 33

What would imply a change to the ART Budget?

A.

Extending the duration of a PI.

B.

Changing total ART resources

C.

Switching to a different PI cadence.

D.

Reducing the scope of a Program Epic.

E.

Prioritizing Features based on Cost of Delay.

Full Access
Question # 34

(Select 2) What are the ways to evolve the Solution Intent from variable to fixed scope?

A.

Creating work breakdown structures.

B.

Modeling

C.

Adapting WIP limits

D.

Building prototypes

Full Access
Question # 35

What does innovation accounting mean?

A.

Capitalizing the cost of software development using Story points.

B.

Defining, empirically measuring, and communicating the true progress of innovation.

C.

Demoing Stories that come out of the IP Iteration.

D.

Being sure to account for the investment in new product initiatives on a P&L.

Full Access