A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?
In a contiguous properly environment (e. g., where campus backbone cables exist), which two of the following are CRITICAL factors to understand for maintenance and growth purposes? (Select two options.)
During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress"?
Which of the following two items are examples of items associated with a submittal? (Select two options.)
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?
A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?
Which two of the following roles do an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Select two options.)
What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?
During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline
What key elements should be included in the benefits register to achieve this goal?
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
Which of the following is a common application for exothermic welding of earthing (grounding) and bonding conductors?
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.
What is the program manager's next step?
A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer lo which of the following?
An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
A new program is comprised of four component projects. The program manager must assign project managers to each of the tour projects. There are eight potential project managers to consider. What should the program manager do before assigning the project managers?
AI the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company's strategy During the previous year, the company needed to comply with new government regulations that impacted this strategy.
Based on this information, what should the program manager do?
A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?
A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?
A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted lo validate compliance with this new regulation. This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan
What immediate actions should the program manager take?
A project is assigned to a qualified project manager by the program manager I he client rejects the project manager due to a lack of proper qualifications to manage such a project
What should the program manager do next?
A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as
The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation
Which of the following metrics should the PMO capture on a monthly basis?
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
A sponsor decides that the business environment is unfavorable for continuation of a program.
The sponsor asks that the program be closed.
What items should be completed as part of the program's final report?
ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by
A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
A program manager is concerned that a program will be unable to achieve its intended benefits. How should the program manager handle this concern?
A company CEO meets with key customers to learn how they can be better served Alter discovering that some executive team members disagree with each other, the CEO asks the program management office (PWO) to develop a program to better serve key customers based on their strategic importance to the company's long-term goals.
What should the program manager do to establish and successfully manage the program's direction?