Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
Determine the correct formula and date for the late finish for Activity 9004.
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
Each of the following accurately describes total float in a schedule EXCEPT:
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
At the end of month one, did the delay to the parking structure foundation delay the project?
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
Which of the following will always describe the critical path? The path with
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
Which of the following parties is NOT a stakeholder of the Spring Highway project?
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
What owner action could have mitigated the late completion of the project?
Determine the correct formula and date for the late finish for Activity 2001.
What project cost elements would NOT normally be reflected in the Activity 1000?
Which is NOT an industry-recognized methodology for quantifying critical delay?