Question # 4

Who is in the best position to decide if Kanban may be a valuable complementary practice for a Scrum Team?

(choose the best answer)

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner

E.

Stakeholders

Full Access
Question # 5

How do Work in Progress (WIP) Limits relate to self-management?

(choose the best two answers)

A.

WIP Limits inhibit self-management since they limit the team's autonomy to pull

work.

B.

WIP Limits provide a boundary/container in which the Scrum Team self-

manages.

C.

A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.

D.

As part of self-managing, Scrum Teams figure out their own WIP Limits.

Full Access
Question # 6

Which statements best describe the purpose of a Scrum Team’s Definition of Workflow?

(Choose the best three answers)

A.

It defines how value flows through the system.

B.

It helps Service Request Manager track the percent completeness of a work item.

C.

It provides a mutual understanding of when the work is considered to be started and finished.

D.

It makes handoff policies explicit by defining clear quality gates between the development stages.

E.

It is used as a checklist of all the states that every work item should go through before it is considered to be done.

F.

It creates transparency over the Work in Progress (WIP) limiting rules.

Full Access
Question # 7

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Full Access
Question # 8

When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?

A.

Using Kanban boards that improve visualization and enhance communication.

B.

None, Professional Scrum with Kanban cannot be used without explicit WIP Limits.

C.

Building a strong team identity using Squads and tribes.

D.

Conducting Daily Stand-Up meetings that control not having too much work.

Full Access
Question # 9

Which of the following are leading indicator metrics?

(choose the best two answers)

A.

Cycle Time.

B.

Service Level Expectation.

C.

Work in Progress.

D.

Work Item Aging.

E.

Monte Carlo.

Full Access
Question # 10

A cumulative flow diagram can show you:

(Choose the best two answers)

A.

The total amount of Work in Progress (WIP) for a specific date.

B.

The average Throughput for a specific date range.

C.

The Cycle Time for an item that completed on a specific date.

D.

The exact average Cycle Time for all items completed on a specific date.

Full Access
Question # 11

Which of these are typically included in the Definition of Workflow policies?

(Choose the best six answers)

A.

Visualization policies.

B.

Pull/prioritization policies.

C.

Service Level Expectations.

D.

WIP limits.

E.

Burndown chart.

F.

The Increment.

G.

Work Item types.

Full Access
Question # 12

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

(choose the best answer)

A.

Throughput.

B.

Story points delivered.

C.

Cycle Time.

D.

Number of Product Backlog items finished in a Sprint.

Full Access
Question # 13

When is the most appropriate time for Scrum Teams practicing professional Scrum with

Kanban to inspect and adapt their Work in Progress (WIP) Limits?

(choose the best answer)

A.

Anytime the Developers see fit.

B.

Never. Once set, WIP Limits cannot be modified.

C.

Every day during Daily Scrum.

D.

During the Sprint Retrospective.

Full Access
Question # 14

True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal

during their Daily Scrum changes.

A.

True

B.

False

Full Access
Question # 15

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD, Control Chart and Aging chart.

C.

Inspecting and adapting the Product Backlog during the Sprint Review.

D.

Reducing the amount of work in progress by introducing Work in Progress (WIP)

Limits.

Full Access
Question # 16

Which of the following are Kanban practices for Scrum?

(choose the best answer)

A.

Visualizing flow, limiting WIP, actively managing the Work in Progress (WIP),

inspecting & adapting the Workflow.

B.

Kaizen, remove delays, visualize policies, pull system.

C.

Small batches, limit WIP, eliminate waste, Kaizen.

D.

Class of service, cost of delay, visualize the Workflow, limit WIP, manage flow.

E.

T-shirt size estimation, service level expectations, limit WIP.

Full Access
Question # 17

Which of the following should NOT be in the Definition of Workflow?

(choose the best answer)

A.

Agreed owner of Workflow lane.

B.

Work in Progress (WIP) Limits.

C.

End of the Workflow.

D.

Start of the Workflow.

Full Access
Question # 18

What are possible benefits of supplementing Scrum with Kanban practices?

(choose the best four answers)

A.

May result in greater collaboration within the Scrum Team.

B.

Scrum Teams no longer need the Sprint time box.

C.

May reduce the average Cycle Time.

D.

Introduces better transparency into state of Work in

Progress (WIP).

E.

May help to discover areas of variability within your Sprint.

F.

Removes the need for the Sprint Planning event.

G.

Allows teams to release multiple times a Sprint.

Full Access
Question # 19

Scrum Teams using Kanban can start to increase predictability by:

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD: Control Chart and Aging chart.

C.

Reducing the amount of work in progress by introducing Work in Progress (WIP) Limits.

D.

Inspecting and adapting the Product Backlog during the Sprint Review.

Full Access
Question # 20

What is true about the Sprint Goal if the Developers reserve capacity for unplanned work during

an upcoming sprint?

(choose the best answer)

A.

The Sprint Goal no longer helps the Developers. They do not know what they will be

working on.

B.

The Developers should never reserve more than 5% capacity for unplanned work. It

is inefficient if the Developer's forecast does not take into account all of their

capacity.

C.

The Sprint Goal becomes more important. It can help the Developers maintain their

focus as new Product Backlog items are brought into the Sprint Backlog.

Full Access
Question # 21

What is Kanban?

(choose the best answer)

A.

A methodology aimed at visualizing your Workflow for effectiveness and enhance

productivity within the team.

B.

A strategy for optimizing the flow of value through a process that uses a visual, Work

in Progress (WIP) limited pull system.

C.

A set of practices that are additive to the Scrum framework.

D.

None of the above.