Question # 4

Why is it crucial that the Project Product Description clearly defines acceptance methods?

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Full Access
Question # 5

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Full Access
Question # 6

Which is a type of issue?

A.

A lesson

B.

A request for change

C.

An Exception Report

D.

A risk with an estimated high impact

Full Access
Question # 7

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Full Access
Question # 8

Which is part of quality control?

A.

Undertake quality reviews

B.

Write Product Descriptions

C.

Provide assurance that the project is being conducted properly

D.

Document the customer's quality expectations

Full Access
Question # 9

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Full Access
Question # 10

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Full Access
Question # 11

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Full Access
Question # 12

Which is an objective of the Closing a Project process?

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project

Full Access
Question # 13

In what process is the authorization to deliver the project's products given?

A.

Starting up a Project

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Directing a Project

Full Access
Question # 14

Which is a recommended quality review team role?

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Full Access
Question # 15

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A.

Project Brief

B.

Project Initiation Documentation

C.

Project mandate

D.

Benefits Review Plan

Full Access
Question # 16

Which is NOT considered when defining risk tolerance?

A.

A Project Board's attitude towards risk taking

B.

The allocated risk budget

C.

An organization's risk appetite

D.

The amount of risk a Project Board considers acceptable

Full Access
Question # 17

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Full Access
Question # 18

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Full Access
Question # 19

Which is a benefit of using PRINCE2?

A.

Enables the management of projects as well as of 'business as usual' activities

B.

Can be tailored by leaving out elements of the method for some projects

C.

Can be applied to any type of project

D.

Avoids the need to involve corporate or programme management

Full Access
Question # 20

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Full Access
Question # 21

What is an off-specification?

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Full Access
Question # 22

What is a benefits management approach used to assess?

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Full Access
Question # 23

What is the project manager role responsible for?

A.

Approving the completion of each management stage

B.

Ensuring that the project produces the required products

C.

Defining the project-level tolerances

D.

Verifying that the project gives value for money

Full Access
Question # 24

Which is a purpose of the 'directing a project' process?

A.

To exercise overall control over the project

B.

To take corrective action to control risks and issues

C.

To do the minimum in order to decide whether the project is feasible

D.

To update the project plan before the next stage

Full Access
Question # 25

Which is a purpose of the change theme?

A.

To prevent change to baselined products

B.

To identify, assess and control any potential and approved changes to baselined products

C.

To establish mechanisms to monitor and compare actual achievements against those planned

D.

To assess and control uncertainty

Full Access
Question # 26

Which product identifies how often stakeholders require information?

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Full Access
Question # 27

What is described as an organization's unique attitude towards risk taking

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Full Access
Question # 28

Which describes a risk event?

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Full Access
Question # 29

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Full Access
Question # 30

Which is a key decision made during the 'directing a project' process?

A.

Select and appoint the project executive

B.

Approve the project manager role description

C.

Confirm that the benefits management approach addresses all expected benefits

D.

Approve the proposed project mandate

Full Access
Question # 31

What should be considered when defining the number of management stages in a project?

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Full Access
Question # 32

What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 33

Which are objectives of the 'managing a stage boundary' process?

1. To control the link between the people managing the project and the people producing the products

2. To approve requests for change received during the completed stage

3. To provide information to the project board on the performance of the current stage

4. To review and, if necessary, update the project management team structure and role descriptions

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 34

Which is a minimum requirement for applying the quality theme?

A.

Appraisal methods of quality control must be carried out on products

B.

A record must be kept of all the quality management activities that are planned

C.

The quality review technique must be used when reviewing products

D.

The quality management approach must align with corporate standards

Full Access
Question # 35

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

A.

Directing a project

B.

Managing product delivery

C.

Managing a stage boundary

D.

Initiating a project

Full Access
Question # 36

Which is a benefit of using PRINCE2?

A.

Is a method specifically designed for technical projects

B.

Provides for the efficient and economic use of management time

C.

Includes many of the proven planning techniques, such as critical path analysis

D.

Can be used to manage both projects and programmes

Full Access
Question # 37

What information should be recorded in the quality register?

A.

Planned activities to determine whether the products are fit for purpose

B.

Potential threats to the project's objectives and how they will be managed

C.

Lessons that the project will capture and use during the project

D.

Off-specifications that will occur during the project

Full Access
Question # 38

Which is a purpose of the 'managing a stage boundary' process?

A.

To enable the project board to approve the continuation of the project

B.

To exercise overall control over the project while delegating day-to-day management

C.

To assign work to be controlled by the team manager

D.

To define the work that needs to be done to deliver the project product

Full Access
Question # 39

Which should be funded from a change budget?

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Full Access
Question # 40

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Full Access
Question # 41

Which is a purpose of a Project Product Description?

A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what the project must deliver in order to gain acceptance

Full Access
Question # 42

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

A.

Product Description

B.

Team Plan

C.

Work Package

D.

Stage Plan

Full Access
Question # 43

Which is an objective of the Initiating a Project process?

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequent stages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project

Full Access
Question # 44

Which is the purpose of the Change theme?

A.

Prevent change to baselined products

B.

Identify, assess and control any potential and approved changes to baselined products

C.

Establish mechanisms to monitor and compare actual achievements against those planned

D.

Assess and control uncertainty

Full Access
Question # 45

What takes place during the Closing a Project process?

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Full Access
Question # 46

Which is a purpose of the Managing Product Delivery process?

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Full Access
Question # 47

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Full Access
Question # 48

How many roles make up the Project Board?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 49

Which should be funded by a change budget?

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Full Access
Question # 50

Which is an objective of the 'starting up a project' process?

A.

To approve the initiation stage

B.

To select the project mandate

C.

To define the project quality management approach

D.

To appoint the project management team

Full Access
Question # 51

Which statement describes the 'Implement' step within the recommended risk management procedure?

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Full Access
Question # 52

Why is a project brief produced?

A.

To act as a trigger for the 'starting up a project' process

B.

To record the how the project will communicate with its stakeholders

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the project board as a basis for reviewing the progress of a project

Full Access
Question # 53

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

A.

Project mandate

B.

Initiation stage plan

C.

Project initiation documentation

D.

Project brief

Full Access
Question # 54

According to PRINCE2, which characteristic is necessary for an effective project board?

A.

An ability to delegate

B.

An attention to detail

C.

A calm management style

D.

A 'problem-solving' approach

Full Access
Question # 55

Within which integrated element does PRINCE2 set minimum requirements?

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Full Access
Question # 56

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

A.

are below the agreed change budget

B.

are objected to by team members

C.

are rejected by the change authority

D.

exceed the agreed change budget

Full Access
Question # 57

Which is a minimum requirement for applying the quality theme?

A.

To define the project's approach to quality control

B.

To undertake independent audits of the project throughout the project

C.

To apply the recommended quality review technique

D.

To define the project's approach to quality assurance

Full Access
Question # 58

Which is a purpose of the 'initiating a project' process?

A.

To decide if it is worthwhile to initiate a project

B.

To decide on the project approach

C.

To establish solid foundations for a project

D.

To identify the number of work packages required

Full Access
Question # 59

Which theme verifies that a project's products are fit for purpose?

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Full Access
Question # 60

Which statement about time-driven controls is CORRECT?

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Full Access
Question # 61

As a minimum requirement for applying the risk theme, what must specifically be assessed?

A.

Whether a risk may cause the project to exceed its cost tolerance

B.

Whether a risk may affect the project-level quality tolerances

C.

Whether a risk may impact the underlying technical assumptions

D.

Whether a risk may alter the project's business justification

Full Access
Question # 62

Who represents the three project interests on a project?

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Full Access
Question # 63

Which describes an off-specification?

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

E.

That the right people are involved in appropriate roles

Full Access
Question # 64

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A.

Team Plan

B.

Stage Plan

C.

Benefits Review Plan

D.

Project Plan

Full Access
Question # 65

Which is a minimum requirement for applying the quality theme?

A.

To use lessons to inform quality planning

B.

To use the prescribed approach to quality management

C.

To use external quality standards for quality control

D.

To use user stories to inform the project product description

Full Access
Question # 66

Which approach must be followed as a minimum requirement for applying the plans theme?

A.

Activity-based planning

B.

Product-based planning

C.

Agile

D.

Risk management

Full Access
Question # 67

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Full Access
Question # 68

Where should a team manager look for information about the quality required for a product?

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Full Access
Question # 69

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

A.

project assurance

B.

the project board

C.

the corporate, programme management or the customer

D.

a team manager

Full Access
Question # 70

During the ‘initiating a project’ process, who specifies the required level of management control?

A.

Corporate, programme management or customer

B.

Project board

C.

Project manager

D.

Project assurance

Full Access
Question # 71

Which is a purpose of the 'controlling a stage' process?

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Full Access
Question # 72

Which is a benefit of using PRINCE2?

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Full Access
Question # 73

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Full Access
Question # 74

Which is a responsibility of the project board?

A.

To manage the team managers and project support

B.

To ensure production of the project's outputs

C.

To ensure effective communication with external stakeholders

D.

To implement the change control approach

Full Access
Question # 75

Whitt is 3 purpose of the initiating a project’ process?

A.

To prepare the contract for the project to enable the project board to commit to delivery

B.

To provide the project board with Just Enough Information to decide whether to approve the Initiation stage

C.

To provide the opportunity for the senior user in confirm that they find the project product acceptable

D.

To enable the project board to empower the project manager to work within delegated authority limits

Full Access
Question # 76

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Full Access
Question # 77

Which is an assumption about the PRINCE2 customer/supplier environment?

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Full Access
Question # 78

What must be done for a project to be a PRINCE2 project?

A.

The project must form part of a programme or portfolio

B.

The project must meet the minimum requirements for applying the themes

C.

The project must use the recommended approach to planning

D.

The project roles must be combined wherever possible

Full Access
Question # 79

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

A.

To plan the activities of the closing a project' process

B.

To implement any exception plan requests from the project board

C.

To create a benefits management approach for corporate, programme management or the customer

D.

To review an issue received from a team manager

Full Access
Question # 80

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Full Access
Question # 81

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

Full Access
Question # 82

Which is a purpose of the 'directing a project' process?

A.

To create and authorize the project mandate

B.

To ensure that work on products allocated to the team is authorized and agreed

C.

To control the day-to-day running of the project

D.

To delegate day-to-day management of the project to the project manager

Full Access
Question # 83

Who is responsible for documenting any tailoring of the business case theme?

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Full Access
Question # 84

How often should the 'controlling a stage' process be used during a project?

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Full Access
Question # 85

What is the minimum number of management stages required by PRINCE2?

A.

Two stages: to initiate and to deliver the project

B.

One stage: to cover the whole project

C.

Three stages: to initiate, to deliver and to close the project

D.

Four stages: to start, to initiate, to deliver and to close the project

Full Access
Question # 86

Which are reasons for a benefits management approach?

1. To state how improvements will be measured

2. To confirm that the benefits are realized

3. To estimate the costs of improvement

4. To define the reason for delivering the improvement

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 87

What is an advantage of applying the 'manage by stages' principle?

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Full Access
Question # 88

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 89

Who are considered as the stakeholders in a project?

A.

Only those benefitting the project

B.

Everyone in the corporate organization

C.

Everyone involved in or affected by the project

D.

Only those who are users of the products

Full Access
Question # 90

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Full Access
Question # 91

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Full Access
Question # 92

Which is a minimum requirement for applying the quality theme?

A.

To define the project’s approach to quality assurance

B.

To appoint external reviewers for quality reviews

C.

To define quality criteria in product descriptions

D.

To provide administrative support for quality controls

Full Access
Question # 93

Which process is used by the project board to respond to on exception report?

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Full Access
Question # 94

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Full Access
Question # 95

Which statement about project roles is CORRECT?

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Full Access
Question # 96

What is the change authority role permitted to authorize?

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Full Access
Question # 97

What must be produced to meet the minimum requirements when applying the change theme?

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Full Access
Question # 98

Which statement about the length of management stages in a project is CORRECT?

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Full Access
Question # 99

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 100

How can the risk culture of 3n organization make decision-making less effective?

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk

Full Access
Question # 101

What is an advantage of applying the 'learn from experience' principle?

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Full Access
Question # 102

What is a risk actionee responsible for?

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Full Access
Question # 103

What does qualitative analysis of a risk assess, as a minimum?

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Full Access
Question # 104

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Full Access
Question # 105

How should the ‘progress’ practice be used?

A.

To define how the products will be delivered to enable control

B.

To predict whether the benefits will exceed the costs

C.

To identify opportunities that may make the project more successful

D.

To deliver change which will benefit people in their day-to-day work

Full Access
Question # 106

Which process should be Used to confirm that the project continues to deliver against the strategic objectives?

A.

Managing a stage boundary

B.

Managing product delivery

C.

Initiating a project

D.

Closing a project

Full Access
Question # 107

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Full Access
Question # 108

Which is a description of a purpose of the communication management approach?

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Full Access
Question # 109

Which action contributes to achieving the ‘ensure continued business justification’ principle?

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Full Access
Question # 110

Which is definition of culture?

A.

The set of shared attitudes, values, goals, and ways of working that characterize a group of people

B.

The process when people from across the project ecosystem work together

C.

An essential aspect of project management that needs to be continually addressed

D.

The tailoring required to take into account the complexity or simplicity of a project

Full Access
Question # 111

What is a description of a leadership activity within a project?

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a team manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Full Access
Question # 112

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

Full Access
Question # 113

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Full Access
Question # 114

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 115

Which is the BEST reason for a PRINCE? project to have at least two stages?

A.

It enables the project team to close the project in an orderly fashion

B.

it enables the project board to decide whether to proceed with the delivery of the project product

C.

It enables the project team to change the scope of the project by agreeing the impact on the business case

D.

It enables the project board to approve the appointment of external contractors, when required

Full Access
Question # 116

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Full Access
Question # 117

How does product-based planning help to determine the project approach?

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Full Access
Question # 118

Which statement describes a purpose of the 'starting up a project’ process?

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Full Access
Question # 119

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Full Access
Question # 120

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Full Access
Question # 121

What is a description of a purpose of the ‘quality’ practice?

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Full Access
Question # 122

Which control is time-driven?

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Full Access
Question # 123

The project manager reviews the project product description to identify the detailed requirement for each product.

In which step of the quality management technique should the project manager do this review?

A.

Gathering user inputs

B.

Accepting products ay

C.

Describing the quality management approach

D.

Controlling quality

Full Access
Question # 124

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Full Access
Question # 125

Which is an internal factor to consider when tailoring PRINCE??

A.

The safety legislation

B.

The environmental standards

C.

The industry's regulations

D.

The organization's procedures

Full Access
Question # 126

Which member of the project management team should secure funding for the project before the project stars?

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Full Access
Question # 127

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Full Access
Question # 128

How do issue management and change control relate to each other?

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

Full Access
Question # 129

Which statement BEST describes how approved plans enable control?

A.

By defining the quality specifications of individual products in product descriptions

B.

By enabling the controlled consideration of business opportunities

C.

By defining the benefits that need to be realized through the benefits management approach

D.

By defining what is within the approved project scope to avoid scope creep

Full Access
Question # 130

Why is change management important in a project?

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Full Access
Question # 131

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Full Access
Question # 132

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Full Access
Question # 133

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?

A.

A work package description

B.

The project management team structure

C.

A stage plan

D.

A work breakdown structure

Full Access
Question # 134

Which is the definition of a requirement?

A.

A need or expectation that has been documented in an approved management product

B.

An event relevant to the project that requires project management consideration

C.

A prediction about future performance made by studying historical data and past patterns

D.

An uncertain event that, should it occur, will have an effect on the project.

Full Access
Question # 135

Which should provide guidance on how and when prototyping is to be used?

A.

Product description

B.

Quality management approach

C.

Quality register

D.

Sustainability management approach

Full Access
Question # 136

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Full Access
Question # 137

What is a purpose of the ‘organizing practice?

A.

To define who is responsible for which project activities

B.

To compare the team's actual achievements against the team plan

C.

Ta understand what the users require of the project

D.

To assess modifications raised by team members

Full Access
Question # 138

What is the BEST reason to perform the risk practice?

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives