Why is it crucial that the Project Product Description clearly defines acceptance methods?
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
In what process is the authorization to deliver the project's products given?
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
What is described as an organization's unique attitude towards risk taking
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
What should be considered when defining the number of management stages in a project?
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
What product is used to maintain a record of those who have an interest in the project and their information requirements?
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
Which statement describes the 'Implement' step within the recommended risk management procedure?
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
According to PRINCE2, which characteristic is necessary for an effective project board?
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
As a minimum requirement for applying the risk theme, what must specifically be assessed?
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
Which approach must be followed as a minimum requirement for applying the plans theme?
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
Where should a team manager look for information about the quality required for a product?
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
During the ‘initiating a project’ process, who specifies the required level of management control?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
The project manager reviews whether there has been a Change in the way team members relate to each other.
Which principle is the project manager applying as part of the 'people' element?
How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?
The project manager has created a list of tasks to produce the project's products.
Which step of the ‘organizational design and development’ technique should be informed ty this 1st?
How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?
Who is responsible for documenting any tailoring of the business case theme?
How often should the 'controlling a stage' process be used during a project?
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?
Which process is used by the project board to respond to on exception report?
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
What must be produced to meet the minimum requirements when applying the change theme?
Which statement about the length of management stages in a project is CORRECT?
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits
How can the risk culture of 3n organization make decision-making less effective?
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
Which process should be Used to confirm that the project continues to deliver against the strategic objectives?
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?
Which is a description of a purpose of the communication management approach?
Which action contributes to achieving the ‘ensure continued business justification’ principle?
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
Which is the BEST reason for a PRINCE? project to have at least two stages?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
Which statement describes a purpose of the 'starting up a project’ process?
The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.
In which process should the project manager define this information?
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?
The project manager reviews the project product description to identify the detailed requirement for each product.
In which step of the quality management technique should the project manager do this review?
According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?
Which member of the project management team should secure funding for the project before the project stars?
in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?
The project management team heeds t document quality antral events, such as testing
According to the guidance for effective quality management, haw should the events be documented?
Identify the missing ward in the following sentence.
PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.
The project manager is acting as the team manager and needs to control the work of a team member who reports to them.
Which management product should the project manager use to control this work?
The project manager needs to document how risk management will be undertaken during the project.
In which step of the 'risk management’ technique should the project manager document this?