Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)®

Last Update 23 hours ago Total Questions : 704

The Certified Associate in Project Management (CAPM)® content is now fully updated, with all current exam questions added 23 hours ago. Deciding to include PMI-100 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-100 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-100 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM)® practice test comfortably within the allotted time.

Question # 4

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question # 5

Which tool or technique is used in the Plan Scope Management process?

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Question # 6

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Question # 7

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Question # 8

An input to the Manage Project Team process is:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Question # 9

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Question # 10

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Question # 11

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Question # 12

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Question # 13

In which Process Group are lessons learned documented?

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Question # 14

An input to the Identify Stakeholders process is:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Question # 15

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Go to page: