Which process determines the risks that may affect the project and documents their characteristics?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
The following is a network diagram for a project.
The free float for Activity E is how many days?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Which action should a project manager take to ensure that the project management plan is effective and current?
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
When the business objectives of an organization change, project goals need to be:
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Which schedule development technique modifies the project schedule to account for limited resources?
When cost variance is negative and schedule variance is positive, the project is:
Which technique is commonly used for the Quantitative Risk Analysis activity?
Which items are an output of the Perform Integrated Change Control process?
What defines the portion of work included in a contract for items being purchased or acquired?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
Change requests are processed for review and disposition according to which process?
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Activity cost estimates are quantitative assessments of the probable costs required to:
The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?
A tool and technique used during the Perform Qualitative Risk Analysis process is:
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
Change requests are an output from which Project Integration Management process?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
An imposed date for completion of the project by the customer is an example of a project:
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
Which tool or technique is used to develop the human resource management plan?
Which of the following types of a dependency determination is used to define the sequence of activities?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?
Within project integration management, the statement of work (SOW) references which aspects of the project?
Projects can intersect with an organizationās operations at various points during the product life cycle such as:
For a stakeholder with low interest and high power, the project manager should:
As the project progresses, which of the following is routinely collected from the project activities?
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Which of the following involves making information available to project stakeholders in a timely manner?
Quality and credibility of the qualitative risk analysis process requires that different levels of the riskās probabilities and impacts be defined is the definition of what?
Who is responsible for developing the project management plan and all related component plans?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Which cost estimate technique includes contingencies to account for cost uncertainty?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Which of the following characteristics are found in a functional organizational structure?
Which organizational process assets update is performed during the Close Procurements process?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
When closing a project or phase, part of the process may require the use of which type of analysis?
Those who enter into a contractual agreement to provide services necessary for a project are:
Lessons learned are created and project resources are released in which Process Group?
Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?
The Closing Process Group includes which of the following Knowledge Areas?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Exhibit A is an example of which of the following types of Sequence Activities?
Which of the following is an example of the simplest fixed-price contract?
Which of the following is a complete set of indexed contract documentation, including the closed contract?
A risk that arises as a direct result of implementing a risk response is called a:
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Which of the following is the primary output of the Identify Risks process?
What type of project structure is a hierarchically organized depiction of the resources by type?
The scope of a project cannot be defined without some basic understanding of how to create the specified:
Which of the following is a narrative description of products, services, or results to be delivered by a project?
In the Initiating Process Group, at what point does the project become officially authorized?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
In which Project Management Process Group is the project charter developed?
An issue log is an input to which Project Human Resource Management process?