New Year Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 5

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement

Full Access
Question # 6

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Full Access
Question # 7

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 8

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Full Access
Question # 9

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Full Access
Question # 10

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Full Access
Question # 11

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Full Access
Question # 12

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Full Access
Question # 13

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Full Access
Question # 14

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Full Access
Question # 15

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Full Access
Question # 16

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Full Access
Question # 17

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Full Access
Question # 18

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Full Access
Question # 19

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Full Access
Question # 20

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

A.

Data security

B.

Operational security

C.

Physical security

D.

Digital security

Full Access
Question # 21

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Full Access
Question # 22

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

A.

Avoid

B.

Transfer

C.

Accept

D.

Share

Full Access
Question # 23

Which of the following is a typical characteristic of Scrum?

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Full Access
Question # 24

Which of the following is a characteristic that defines a project?

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Full Access
Question # 25

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

A.

The ticket system provided access by default without any approval.

B.

The project manager did not perform proper project planning.

C.

The system is lacking proper access controls.

D.

Sensitive data was incorrectly classified during the audit process.

Full Access
Question # 26

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Full Access
Question # 27

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Full Access
Question # 28

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Full Access
Question # 29

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Full Access
Question # 30

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Full Access
Question # 31

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

A.

Development

B.

Production

C.

Testing

D.

QA

Full Access
Question # 32

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Full Access
Question # 33

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Full Access
Question # 34

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Full Access
Question # 35

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Full Access
Question # 36

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Full Access
Question # 37

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Full Access
Question # 38

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Full Access
Question # 39

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Full Access
Question # 40

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Full Access
Question # 41

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Full Access
Question # 42

Which of the following can be used to determine whether a sample product is within an acceptable range?

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Full Access
Question # 43

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Full Access
Question # 44

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Full Access
Question # 45

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Full Access
Question # 46

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Full Access
Question # 47

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Full Access
Question # 48

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Full Access
Question # 49

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Full Access
Question # 50

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Full Access
Question # 51

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 52

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Full Access
Question # 53

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Full Access
Question # 54

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Full Access
Question # 55

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

A.

SLA

B.

TOR

C.

SOW

D.

NDA

Full Access
Question # 56

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 57

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Full Access
Question # 58

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Full Access
Question # 59

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Full Access
Question # 60

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Full Access
Question # 61

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Full Access
Question # 62

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Full Access
Question # 63

Which of the following offers administrators more direct control over operating systems?

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

Full Access
Question # 64

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Full Access
Question # 65

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Full Access
Question # 66

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Full Access
Question # 67

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Full Access
Question # 68

Which of the following BEST illustrates how team members with different roles should interact on the team?

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Full Access
Question # 69

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Full Access
Question # 70

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Full Access
Question # 71

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 72

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Full Access
Question # 73

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Full Access
Question # 74

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Full Access
Question # 75

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Full Access
Question # 76

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Full Access
Question # 77

Which of the following can a project manager infer from the following velocity chart?

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Full Access
Question # 78

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 79

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Full Access
Question # 80

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Full Access
Question # 81

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 82

Given the following network diagram:

Which of the following is the critical path?

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Full Access
Question # 83

Which of the following statements best describes a content management system?

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Full Access
Question # 84

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Full Access
Question # 85

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Full Access
Question # 86

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Full Access
Question # 87

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Full Access