11.11 Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

The contractor has submitted waste hauling reports for review in order to achieve Materials and Resources Credit, Construction and Demolition Waste Management. Which of the following materials on the documentation contribute towards the credit?

A.

Excavated soil

B.

Wood derived fuel

C.

Items sent to the local incinerator

D.

Alternate Daily Cover

Full Access
Question # 5

Which of the following transit modes is considered to be walkable if it is within 1/2 mile (0.8 km) of the functional entry of a project?

A.

Taxi stand

B.

Ferry terminal

C.

Local bus stop

D.

Streetcar stop

Full Access
Question # 6

In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?

A.

HVAC air system for air conditioning

B.

Electrical lighting system during peak use hours

C.

Water flow system used for public faucets and toilets

D.

Condenser water system with a cooling tower and condenser water pumps

Full Access
Question # 7

Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to exclude what type of land area from the calculations?

A.

Buildable land within 1/4 mi. (0.40 km) of the project boundary

B.

Public right-of-way areas within 1/4 mi. (0.40 km) of the project boundary

C.

Surface parking areas within 1/2 mi. (0.80 km) of the project boundary

D.

University campus land areas within 1/2 mi. (0.80 km) of the project boundary

Full Access
Question # 8

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Full Access
Question # 9

The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

A.

Use MERV 8 (F5), or higher, filters

B.

Provide a hard-lid ceiling

C.

Create positive pressure in the room

D.

Provide a large opening to dilute air contaminates

Full Access
Question # 10

During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?

A.

Innovation Credit, Innovation

B.

Integrative Process Credit

C.

Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control

D.

Materials and Resources Credit, Interiors Life-Cycle Impact Reduction

Full Access
Question # 11

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a post office and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

Full Access
Question # 12

For an emergency care facility project, which of the following credits can be achieved if the total cost of

permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?

A.

Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Material Reuse

& Innovation Credit, Innovation, Exemplary Performance

B.

Materials and Resources Credit, Furniture and Medical Furnishing, Option 3. Multi-Attribute Assessment of

Products & Innovation Credit, Innovation, Exemplary Performance

C.

Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2.

Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance

D.

Materials and Resources Credit, Furniture and Medical Furnishings, Option 3. Multi-Attribute Assessment of

Products & Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization

Full Access
Question # 13

Which of the following items must have safe collection, storage, and disposal for Materials and Resources Prerequisite, Storage and Collection of Recyclables?

A.

Food waste

B.

Medical waste

C.

Electronic waste

D.

Landscape waste

Full Access
Question # 14

What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U

A.

Coordinate open space features during the construction phase

B.

Minimize the floor-area ratio (FAR) and accessibility for open space

C.

Design a parking and road footprint layout that is not near open land

D.

Coordinate open space features early during the site planning phase

Full Access
Question # 15

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

Full Access
Question # 16

Large commercial buildings are most often dominated by

A.

internal loads

B.

lighting loads

C.

external loads

D.

envelope loads

Full Access
Question # 17

In order for a product to contribute to Materials and Resources Credit, Building Product Disclosure and Optimization, Environmental Product Declarations, Option 1. Environmental Product Declaration, the product needs to be

A.

Forest Stewardship Council (FSC)-certified

B.

cradle-to-cradle certified

C.

third-party verified in a Corporate Sustainability Report (CSR)

D.

critically reviewed life-cycle assessment conforming to ISO 14044

Full Access
Question # 18

Innovation credits for exemplary performance can be awarded for

A.

achieving one pilot credit

B.

achieving double the credit requirements

C.

demonstrating significant environmental benefits

D.

demonstrating a qualitative improvement in environmental performance

Full Access
Question # 19

Which of the following strategies is allowed under Energy Atmosphere Credit, Renewable Energy Production, and will help a project achieve Energy Atmosphere Credit, Optimize Energy Performance?

A.

Install an on-site photovoltaic array

B.

Purchase Green-e certified carbon offsets

C.

Purchase Green-e certified Renewable Energy Certificates (RECs)

D.

Install a ground-source heat pump

Full Access
Question # 20

In pursuit of the Materials and Resources Credit, Building Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, which of the following statements is true related to products purchased for temporary use (formwork, bracing and scaffolding) on the project?

A.

Temporary wood products cannot be included in the calculations

B.

If any temporary wood materials are included in the calculation, all wood materials must be included in the calculation

C.

Only Forest Stewardship Council (FSC)-certified wood materials are included in the calculation; non-certified wood materials contribute to other credits

D.

FSC-certified wood materials purchased for more than one project can be applied to other projects seeking LEED Certification

Full Access
Question # 21

When planning a water-efficient landscape design, the designer should consider including

A.

potable water

B.

sprinkler system

C.

native vegetation

D.

permeable pavement

Full Access
Question # 22

What requirement must be met when creating a Demand Response Program that satisfies Energy and Atmosphere Credit, Demand Response?

A.

Permanently reduce the energy consumption in the building by 5%

B.

Demonstrate submetering of the two highest electrical end uses

C.

Demonstrate a load shift reduction of 5% in the building

D.

Create a comprehensive plan for meeting a demand response event

Full Access
Question # 23

What is the best strategy for a LEED AP to suggest in order to quantify the impact of increasing the window-to-wall ratio on a Building Design and Construction project?

A.

Compare the current project to other similar projects

B.

Monitor the HVAC loads throughout the life of the project

C.

Perform a simple box energy model before the completion of the schematic phase

D.

Review Green Business Certification Inc. (GBCI)'s comments on the energy model submission

Full Access
Question # 24

What is the basis of energy consumption in determining the percentage of green power or carbon offsets?

A.

Quality

B.

Quantity

C.

Efficiency

D.

Performance

Full Access
Question # 25

Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?

A.

Electrical, Mechanical, Plumbing, and Renewable Energy

B.

Electrical, Structural, Mechanical, and Lighting

C.

Electrical, Structural, Audio Visual, and Envelope

D.

Electrical, Plumbing, Telecommunications, and Fire Suppression

Full Access
Question # 26

Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

A.

A standard garbage disposal

B.

Electronic submeter at the domestic water supply pipe to the building

C.

An open-loop HVAC system that discharges potable cooling water to a nearby lake

D.

Commercial dishwasher that is ENERGY STAR® labeled or performance equivalent

Full Access
Question # 27

What is the average flush rate for a dual flush toilet with a high flush rate of 1.6 gpf (6 lpf) and a low flush rate of 1.05 gpf (4 lpf)?

A.

1.05 gpf (4 lpf)

B.

1.19 gpf (4.5 lpf)

C.

1.23 gpf (4.66 lpf)

D.

1.32 gpf (5 lpf)

Full Access
Question # 28

A commercial office building with a footprint of 70,000 ft2 (6 503.2 m2) has an overall site area of 200,000 ft2 (18 580.6 m2). The project design includes 15,000 ft2 (1 393.5 m2) of pedestrian oriented hardscape and 18,000 ft2 (1 672.3 m2) of vegetated open space. Which of the following is necessary to satisfy the requirement for the outdoor space to be physically accessible when calculating the Sustainable Sites Credit, Open Space?

A.

A garden space dedicated to industrial food production for use by local communities

B.

A garden space with only one vegetation type and species during the summer for visual interest

C.

A dark paving area with site elements to encourage parking near wetlands or naturally designed ponds

D.

A pedestrian-oriented paving or turf area with physical site elements that accommodate outdoor social activities

Full Access
Question # 29

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner's Project Requirements (OPR)?

A.

All applicable codes and standards

B.

Interior finishes related to the project

C.

All project team members and applicable roles

D.

Energy efficiency goals and training requirements

Full Access
Question # 30

Sustainable Sites Credit, Site Assessment requires evaluation of

A.

soils, archeology, hydrology

B.

topography, hydrology, human use

C.

vegetation, topography, archaeology

D.

human health effects, climate, land value

Full Access
Question # 31

Every location in the U.S. identifies how many regional credits?

A.

Four

B.

Five

C.

Six

D.

Seven

Full Access
Question # 32

What reference standard is used to determine compliance with the Energy and Atmosphere Prerequisite, Minimum Energy Performance when the whole building energy modeling option is used?

A.

ASHRAE 55-2010

B.

ASHRAE 90.1-2007

C.

ASHRAE 90.1-2010

D.

ASHRAE 62.1-2010

Full Access
Question # 33

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Full Access
Question # 34

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

A.

natural gas

B.

hot water at the main service point

C.

nothing, because the flat fee is included as part of the lease

D.

nothing, because the energy source is outside of the project's scope

Full Access
Question # 35

A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?

A.

Install a preferred drop-off lane for buses meeting the emission requirements

B.

Provide calculations showing that the average fleet bus meets the emission requirements

C.

Inventory the school fleet to develop and create a plan for all buses to meet the emission requirements

D.

Document that all buses serving the project achieve a minimum green score of 30 on the American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide

Full Access
Question # 36

A neighborhood housing development organization has dual goals, promoting occupant's health and minimizing

energy costs. What LEED Building Design and Construction, New Construction credit might the LEED AP propose to best achieve the organization's dual goals?

A.

Location and Transportation Credit, Access to Quality Transit

B.

Energy and Atmosphere Credit, Optimize Energy Performance

C.

Indoor Environmental Quality Credit, Low Emitting Materials

D.

Indoor Environmental Quality Credit, Daylight

Full Access
Question # 37

An office project has the following items in its break room kitchen: a kitchen sink, a residential-style dishwasher, and a coffee machine. How would these items be addressed in Water Efficiency Prerequisite, Indoor Water Use Reduction?

A.

The kitchen sink is included in fixture calculations, the dishwasher and coffee machine must be ENERGY STAR® or performance equivalent

B.

The kitchen sink is included in fixture calculations, the dishwasher must be ENERGY STAR® or performance equivalent, and the coffee machine is not included in the prerequisite

C.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine is not included in the prerequisite

D.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine should be included in fixture calculations

Full Access
Question # 38

A project team wants to educate the facility manager on the installed building systems to improve Indoor Environmental Quality. They want the facility manager to maintain the systems so that they will continue to function as intended. Which of the following should be provided to the facility manager?

A.

Vendor invoices for mechanical equipment

B.

Preventive maintenance plan for the building

C.

As-built drawings and copies of material submittals

D.

A copy of the credit documentation for the credits that were approved by Green Business Certification Inc. (GBCI)

Full Access
Question # 39

The intent of the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention is to £

A.

control erosion, noxious odors and landfill waste

B.

control erosion, landfill waste and excessive noise

C.

control erosion, waterway sedimentation and airborne dust

D.

control erosion, waterway sedimentation and noxious odors

Full Access
Question # 40

Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?

A.

Installing bioretention area

B.

Installing on-site renewable power generation facility

C.

Substituting impervious surface area with high-albedo paving materials

D.

Increase artificial turf on the roof

Full Access
Question # 41

Which of the following methods is the referenced standard for demonstrating compliance with Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

A.

ASHRAE 62.2 - 2007

B.

ASHRAE 90.1 - 2010

C.

ASHRAE 55 - 2010

D.

ASHRAE 62.1 - 2010

Full Access
Question # 42

In order to meet the minimum qualifications for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification a Commissioning (Cx) agent must have completed the commissioning process activities for a minimum of how many similar projects?

A.

Zero

B.

One

C.

Two

D.

Three

Full Access
Question # 43

What is the first step to earn the Water Efficiency Credit, Cooling Tower Water Use?

A.

Select air-conditioner condensate for cooling

B.

Calculate cycles of concentration

C.

Identify the maximum number of cycles for the cooling tower or evaporative condenser

D.

Engage a water treatment professional to perform a chemical analysis

Full Access
Question # 44

The current facilities requirements (CFR) and operations and maintenance plan (OMP) required for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification must include

A.

issue logs

B.

functional performance tests

C.

minimum outside air requirements

D.

installation verification (construction) checklists

Full Access
Question # 45

A project's massing and site orientation can have a direct impact on which of the following prerequisites?

A.

Minimum Energy Performance

B.

Minimum Indoor Air Quality Performance

C.

Construction Activity Pollution Prevention

D.

Fundamental Commissioning and Verification

Full Access
Question # 46

A contractor wants to use an adhesive that exceeds the allowed Volatile Organic Compound (VOC) content limit under Indoor Environmental Quality Credit, Low Emitting Materials. This credit can be earned if

A.

the VOC budget method is applied for VOC content

B.

the adhesive is not included in the LEED documentation

C.

75% of the adhesives used comply with the VOC content limit and emissions requirements

D.

95% of the adhesives used comply with the VOC content limit and emissions requirements

Full Access
Question # 47

In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for

both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?

A.

Flooring

B.

Furniture

C.

Composite wood

D.

Wet applied products

Full Access
Question # 48

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

A.

The general contractor

B.

A LEED AP

C.

The project's mechanical engineer

D.

The owner or an owner's representative

Full Access
Question # 49

Which of the following will contribute to reducing the heat island effect?

A.

Artificial turf grass

B.

Intensive vegetated roof

C.

Steep sloped roof with initial SRI of 35

D.

Low sloped roof with initial Solar Reflectance Index (SRI) of 64

Full Access
Question # 50

Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?

A.

Source control

B.

Material selection

C.

Contractor training

D.

Pre-construction meeting

Full Access
Question # 51

The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because

A.

SRI generally increases with age

B.

SRI generally decreases with age

C.

SRI generally remains the same with age

D.

SRI generally does not impact the Heat Island Effect

Full Access
Question # 52

The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 2. Leadership Extraction Practices

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 1. Raw Material Source and Extraction Reporting

C.

Materials and Resources Credit, Building Product Disclosure and Optimization Environmental Product

Declarations, Option 1. Environmental Product Declarations

D.

Materials and Resources Credit, Construction and Demolition Waste Management, Option 1. Diversion

Full Access
Question # 53

Which would contribute to compliance with Sustainable Sites Credit, Open Space?

A.

A mall with an indoor atrium, featuring a reflective roof

B.

A parking lot that serves as the location for a monthly flea market

C.

An intensive vegetated roof, provided the building has at least a 1.0 Floor to Area Ratio (FAR)

D.

A forested area containing nature trails, that also achieves Sustainable Sites Credit, Site Development – Protect or Restore Habitat

Full Access
Question # 54

Which of the following products must always be included in Materials and Resources credits?

A.

Faucets

B.

Furniture

C.

Interior Paint

D.

Fire suppression system

Full Access
Question # 55

Which of the following are the major factors determining the total irrigation requirement for a particular landscaping design?

A.

Planting density, soil conditions, irrigation efficiency and rainfall

B.

Relative humidity, site exposure, plant species and planting density

C.

Plant species, rainfall, evapotranspiration rate, site exposure and irrigation efficiency

D.

Plant species, rainwater tank size, evapotranspiration rate, site exposure and irrigation efficiency

Full Access
Question # 56

Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?

A.

Ceiling heights

B.

Building furniture

C.

Movable partitions

D.

Permanent interior obstructions

Full Access
Question # 57

A design team is working on a new building project and is employing an integrated, whole-building approach. The architects want to increase the size of a glazed opening on the south facing wall. Which team members are first

affected by this change?

A.

Civil engineers

B.

Facility managers

C.

Landscape architects

D.

Mechanical engineers

Full Access
Question # 58

Which of the following contributes to the value of the commissioning process?

A.

Ensuring that the project budgetary goal is met

B.

Verifying that the building systems perform as intended

C.

Verifying that the building water fixtures are installed properly

D.

Ensuring that the project is delivered to meet the permitting requirements

Full Access
Question # 59

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

A.

Two Level (on, off)

B.

Three Level (on, 25%, off)

C.

Three Level (on, 50%, off)

D.

Three Level (on, 75%, off)

Full Access
Question # 60

Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the conventional approach for rainwater management by

A.

replicating a site's natural hydrology

B.

discharging rainwater at a faster rate

C.

increasing a site's impervious surface

D.

providing a greater volume of rainwater detention

Full Access
Question # 61

A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?

A.

If a rating system is appropriate for less than 50% of the gross area of the LEED project space then the rating system must not be used

B.

If a rating system is appropriate for more than 50% of the gross floor area of LEED project space, then that rating system must be used

C.

If a rating system is appropriate for 30% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

D.

If a rating system is appropriate for 40% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

Full Access
Question # 62

In order to achieve Indoor Environmental Quality Credit, Quality Views the project team increased the window-to-wall

ratio. Which prerequisite was impacted by this action?

A.

Energy and Atmosphere Prerequisite, Minimum Energy Performance

B.

Energy and Atmosphere Prerequisite, Building-Level Energy Metering

C.

Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management

D.

Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification

Full Access
Question # 63

When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

A.

included in the calculation

B.

excluded from the calculation

C.

excluded if the total volume is less than 25% of the building being reused

D.

excluded if the total volume is more than 25% of the building being reused

Full Access
Question # 64

What is the minimum gross floor area required for a Building Design and Construction project to be eligible for

certification?

A.

250 ft2 (23 m2)

B.

500 ft2 (46 m2)

C.

750 ft2 (70 m2)

D.

1000 ft2 (93 m2)

Full Access
Question # 65

The project landscape architect suggests reducing the area planned for surface parking and replacing it with additional vegetated space. What benefit would this strategy provide to the owner?

A.

Increases the rainwater infiltration capacity

B.

Decreases the amount of bicycle parking that must be provided

C.

Increases the overall SR (solar reflectance) of the hardscape area

D.

Decreases the required amount of on-street parking that must be provided

Full Access
Question # 66

Landscape irrigation practices consume large quantities of potable water. By evaluating the project's outdoor water budget and irrigation water demand early in the design process in Water Efficiency Prerequisite, Outdoor Water Use Reduction project teams will be able to

A.

earn Water Efficiency Credit, Water Metering

B.

earn Sustainable Sites Credit, Rainwater Management

C.

estimate and optimize water use in landscape designs

D.

estimate and optimize water use in outdoor fountains and pools

Full Access
Question # 67

What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?

A.

Office

B.

Hospital

C.

Warehouse

D.

Data Center

Full Access
Question # 68

Which energy efficient lamp type is free from mercury?

A.

Compact Fluorescent

B.

High Pressure Sodium

C.

Light Emitting Diode

D.

T-8 Fluorescent

Full Access
Question # 69

The LEED AP has identified a pilot credit that is relevant to the project. This would be documented in LEED Online as a(n)

A.

Exemplary Performance for a related credit

B.

Special Circumstances within a related credit

C.

Regional Priority Credit

D.

Innovation Credit

Full Access
Question # 70

Which site preparation and construction method contributes to earning the Materials and Resources Credit, Construction and Demolition Waste Management?

A.

Reuse excavated soil and land-clearing debris

B.

Implement in situ soil remediation and post removal of the existing concrete pavement

C.

Salvage and recycle 50% of the existing materials (based on volume) generated during site demolition for three material streams

D.

Ensure reduction of pollution from construction activities by using airborne dust generation capture systems

Full Access
Question # 71

Which of the following strategies can be used to decrease the envelope load of a building?

A.

Provide summer solar shading

B.

Maximize daylighting

C.

Decrease opaque wall area

D.

Use economizers for free cooling

Full Access
Question # 72

Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?

A.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior Lighting

B.

Indoor Environmental Quality Credit, Low-Emitting Materials and Sustainable Sites Credit, Site Assessment

C.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Minimum Indoor Environmental Quality Performance

D.

Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies and Indoor Environmental Quality Prerequisite, Minimum Indoor Environmental Quality Performance

Full Access
Question # 73

What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?

A.

LEED v4, LEED for Neighborhood Development Conditional Approval

B.

LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project

C.

LEED for Neighborhood Development Pilot, Stage 1 LEED for Neighborhood Development Pre-reviewed Plan

D.

LEED 2009, Stage 1 Conditional Approval of LEED for Neighborhood Development Plan

Full Access
Question # 74

A project elects to pursue Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses because of the project's location in an amenity-rich area. The project features 18 uses overall, including at least four uses in three of the five use type categories. What threshold must the project surpass in order to demonstrate exemplary performance for Option 2?

A.

Exemplary Performance is not available for Option 2

B.

15 uses, including two uses in each of the five categories

C.

15 uses, including at least one Food Retail and one Community Anchor use

D.

18 uses, including uses in at least four of the five use type categories

Full Access
Question # 75

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

Full Access
Question # 76

What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?

A.

Schools

B.

Data centers

C.

Hospitality

D.

Warehouses and distribution centers

Full Access
Question # 77

Building Product Disclosure and Optimization is based on market

A.

reliability

B.

durability

C.

transparency

D.

consumption

Full Access
Question # 78

For a task chair purchased for a healthcare facility, which portion of the product contributes toward Materials and Resources Credit, Furniture and Medical Furnishings?

A.

Wheels, 4% of product by weight, that do not contain lead, mercury, cadmium or antimony

B.

Fabric, 5% of product by weight, with stain resistant treatment containing Perfluorinated Compounds (PFCs)

C.

Metal base, 20% of product by weight, which do not contain heavy metals and is not plated with hexavalent chromium

D.

Plastic armrests, 30% of product by weight, with added antimicrobial treatment

Full Access
Question # 79

A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?

A.

$90

B.

$225

C.

$360

D.

$405

Full Access
Question # 80

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Full Access