Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

A residential client wants to build an addition that would occupy the entire side-yard. What is the interior designer responsible for checking before proceeding?

A.

soils report

B.

access route

C.

setback requirement

D.

neighborhood agreement

Full Access
Question # 5

The specification of which item is within the scope of work for interior designers when designing for water conservation?

A.

ultra-low flow faucets

B.

vegetated roof system

C.

rainwater collection cisterns

D.

FSC certified wood products

Full Access
Question # 6

How are the actual riser and tread dimensions for a set of stairs determined?

A.

Divide floor opening by desired tread dimension

B.

Divide floor opening by desired riser dimension

C.

Divide floor-to-floor height by minimum riser dimension

D.

Divide floor-to-floor height by maximum riser dimension

Full Access
Question # 7

During construction, the general contractor notices conflicting information between the construction drawings and the specifications. The FIRST step the contractor should take is to

A.

issue a change order

B.

make an interpretation

C.

notify the owner of the discrepancy

D.

notify the designer of the discrepancy

Full Access
Question # 8

A project is running behind schedule and over budget. What should the designer do FIRST?

A.

Review and determine budget cuts with the client

B.

Simplify installation methods to save both cost and time

C.

Contact the client to discuss the problem as soon as possible

D.

Rank construction priorities and complete the critical path elements first

Full Access
Question # 9

A university is renovating the restrooms (washrooms) of a dormitory built in 1963 and is required to reduce the water usage by 20%. What is MOST important when specifying plumbing fixtures?

A.

durability & Green Seal fixtures

B.

cleanability & Energy Star fixtures

C.

accessibility & WaterSense fixtures

D.

sustainability & International Plumbing Code compliant fixtures

Full Access
Question # 10

What are the three parts of a Construction Specification Institute (CSI) specification?

A.

general, products, execution

B.

allowance, alternate, application

C.

information, purchasing, installing

D.

requirements, finishes, construction

Full Access
Question # 11

Several employees in an office suffer from pollen allergies. How could their symptoms be reduced while at work?

A.

Install non-operable windows

B.

Install high-efficiency air filters

C.

Utilize a passive ventilation system

D.

Relocate these employees to internal offices

Full Access
Question # 12

To reduce radon levels in a home, it is recommended that the

A.

crawl space is ventilated

B.

building is depressurized

C.

basement windows are sealed

D.

expansion joints are installed at slabs-on-grade

Full Access
Question # 13

Which person is MOST responsible for ensuring that the construction drawings are code-compliant?

A.

Developer

B.

Building owner

C.

Interior designer

D.

Building inspector

Full Access
Question # 14

The installation of which material has the lowest VOC emissions?

A.

epoxy paint

B.

ceramic tile

C.

vinyl wallcovering

Full Access
Question # 15

A mock-up is provided after client review of the finishes and systems furniture components. Upon inspection of the mock-up, the client observes that the fabric on the panels does not match their corporate standards. What should the designer do NEXT?

A.

Explain to the client that the mock-up cannot be altered

B.

Verify in the meeting minutes which finishes were selected

C.

Request the furniture dealership to reproduce the mock-up

D.

Review the fabric submittal to ensure it works with the application

Full Access
Question # 16

Which type of mechanical heating system uses pipes or tubing embedded within the ceiling, floor, or wall construction?

A.

electric

B.

radiant

C.

hot-water

D.

forced-air

Full Access
Question # 17

A designer is planning an office remodel where the tenant is relocating their existing microwaves. After project completion, the tenant is disappointed to discover the outlets for the microwaves were installed at the incorrect height. What could the designer have done to prevent this?

A.

Coordinated the outlet heights with the electrical drawings

B.

Requested an appliance submittal from the general contractor

C.

Scheduled a site walk with the electrical contractor during installation

D.

Verified the equipment specifications with the microwave manufacturer

Full Access
Question # 18

At the time of preparing construction documents, the client is undecided about replacing flooring within the scope of work. How would the designer obtain pricing for including the flooring?

A.

a mock-up

B.

an alternate

C.

an addendum

D.

a change order

Full Access
Question # 19

During demolition, the contractor discovers dry rot in some existing walls that are to remain. After reaching an agreement with the client and contractor on a solution, what should be issued before construction continues?

A.

a bulletin

B.

an addendum

C.

a change order

D.

a change directive

Full Access
Question # 20

Design time has exceeded what was estimated when determining the fixed-fee contract. Whatshould be done?

A.

Proceed with fees designated in the contract

B.

Negotiate a new contract and fee agreement

C.

Stop work until a new agreement can be negotiated

D.

Attach time sheets to the invoice to clarify additional fees

Full Access
Question # 21

A building code official has declined to issue a building permit for a project. The official explains that the plans and specifications do not meet code in terms of partition fire ratings and finishes. In order to keep the project on schedule, what would be the FIRST step in dealing with the problem?

A.

File an appeal with the city

B.

Notify the client immediately

C.

Notify the contractor by phone

D.

Discuss the problem with the code official

Full Access
Question # 22

A restaurant is designated as which occupancy classification?

A.

public: group P-3

B.

business: group B

C.

restaurant: group R

D.

assembly: group A-2

Full Access
Question # 23

While on site, the designer notices that the glazing subcontractor is installing the storefront system in the wrong finish. What should the designer do?

A.

Report the discrepancy in a memo to the contractor and client

B.

Reach out to the glazing supplier to find out which finish was ordered

C.

Explain the issue at the next owner, architect, contractor (OAC) meeting

D.

Tell the subcontractor to stop their work and explain the issue to the contractor

Full Access
Question # 24

Formaldehyde, PVC, and phthalates are examples of chemicals included in

A.

The Red List

B.

Class C finishes

C.

Hazardous building types

D.

CAL 133 compliant products

Full Access
Question # 25

A client has signed a lease for a ground floor space previously used as a mobile phone retail store and plans to convert the space into a medical office. The designer should FIRST

A.

contact the building department to confirm if this use is permitted

B.

request programming information from the client and generate test fit plans

C.

survey existing space and ensure site conditions match up with CAD background

D.

confirm if the occupancy type above the space will trigger a fire separation requirement

Full Access
Question # 26

Changes made to the contract documents during the bid (tender) process are documented in a(n)

A.

Bulletin

B.

Addendum

C.

Change order

Full Access
Question # 27

A designer who is working on a non-profit community center in a historic building has met individually with the project’s benefactor, the community center’s board, the center’s director and staff, local community members, the municipality’s historic preservation committee, and the retained contractor. Which of the following is the designer’s GREATEST challenge?

A.

Balancing the various stakeholders’ preferences

B.

Working with the contractor towards a unique design

C.

Balancing material and finishes that have historical significance

D.

Working with the community towards a concept that will use the space as desired

Full Access
Question # 28

What modification would increase the available time for occupants to exit a space during a fire?

A.

Change the ceiling type

B.

Install a sprinkler system

C.

Increase the number of exits

D.

Specify finishes with higher flame-spread rating

Full Access
Question # 29

Upon review of all consultants’ drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?

A.

Provide the dimensions of the water closet along with a notation on the interior design documents of the water closet’s new location

B.

Coordinate the proper location with all parties through a change order

C.

Coordinate with the mechanical engineer and have the water closet relocated on the engineer’s drawings

D.

No action is necessary because the contractor is obliged to follow the interior design documents

Full Access
Question # 30

What do written specifications define?

A.

quantity

B.

form

C.

quality

D.

relationship

Full Access
Question # 31

What is the term for a full-scale representation of products or construction features that may be required in bid (tender) documents?

A.

models

B.

samples

C.

mock-ups

D.

shop drawings

Full Access
Question # 32

A project is considered substantial and complete when

A.

Partial occupancy has been issued

B.

Deficiencies have been documented

C.

Progress payments have been administered

D.

The owner can use it for its intended purpose

Full Access
Question # 33

The design for a new corporate office has wood wall panels with aluminum reveals. What sequence below will result in the MOST efficient installation?

A.

Installation of panels then reveals

B.

Installation of base then wood wall panels

C.

Installation of inner wall blocking then reveals

D.

Installation of reveals then inner wall blocking

Full Access
Question # 34

The interior designer presents budget options based on quality ranges and the client approves a budget on the low end. Throughout the design process, the client has added higher quality items and the project is now over budget. What could have been done to prevent this problem?

A.

Included a contingency line item in the budget

B.

Required the client to fill out preliminary budget sheets

C.

Reviewed the budget status more frequently with the client

D.

Redefined the specifications based on a square foot budget

Full Access
Question # 35

What method of payment for interior design services poses the least financial risk to the designer?

A.

time-based fee

B.

fixed design fee

C.

value-based fee

D.

retail sales-based fee

Full Access
Question # 36

The conservation of water through landscaping with native plants and mulching is called

A.

xeriscaping

B.

terrascaping

C.

aquascaping

D.

greenscaping

Full Access
Question # 37

For a public restroom (washroom) design, which wall base is the BEST option for cleanability?

A.

6" [152 mm] high rubber wall base

B.

4" [102 mm] high ceramic tile base

C.

Vinyl wallcovering that starts 1/4" [6 mm] above finished floor (AFF)

D.

Solid surface wall panels that start 2" [51 mm] above finished floor (AFF)

Full Access
Question # 38

A designer has a contract with a client to provide complete contract documents for a tenant build-out. Specifying FF&E is beyond the scope of the contract. The designer makes some general FF&E recommendations to show a systems furniture layout as required by the local code officials. The furniture comes in over the client’s previously undisclosed budget. What should the designer do?

A.

Suggest that the client purchase directly from the manufacturer

B.

Meet with the client and furniture provider to resolve the problems

C.

Research alternate furniture options to bring the budget back in line

D.

Let the client and the furniture provider work out the budget problems

Full Access
Question # 39

What is the allowable reach range for an obstructed side reach over a kitchen counter?

A.

34" [914 mm] to 46" [1168 mm]

B.

15" [381 mm] to 48" [1219 mm]

C.

18" [457 mm] to 48" [1219 mm]

Full Access
Question # 40

What is the rentable square footage [m²] of a building?

A.

the tenant suite not including any common and shared areas of a building

B.

the tenant suite including all of common areas of a building such as lobbies, corridors, hallways and restrooms (washrooms)

C.

the tenant suite including a percentage of common areas of a building such as lobbies, corridors, vertical penetrations, hallways and restrooms (washrooms)

D.

the common and shared areas of a building such as lobbies, corridors, stairwells, meeting rooms, hallways and restrooms (washrooms) used by all building tenants

Full Access
Question # 41

A new hospital includes a cafeteria and a 60-person conference room. Which occupancy classifications would apply?

A.

assembly and business

B.

assembly and industrial

C.

institutional and business

D.

institutional and assembly

Full Access
Question # 42

With regard to electrical systems, one responsibility of an interior designer is to provide the

A.

Quantity of junction boxes for light fixtures

B.

Quantity of conduit for wiring under carpet

C.

Location of electrical panel and circuit breakers

D.

Location of power required for built-in equipment

Full Access
Question # 43

A post-occupancy evaluation indicates that occupants are cold during winter months due to the building’s HVAC system not performing according to design. What would have prevented this situation?

A.

commissioning

B.

additional diffusers

C.

a punch (deficiency) list

D.

an underfloor distribution system

Full Access
Question # 44

A storage area has been approved as an accessory occupancy within a retail store. The means of egress requirements are based on which occupancy type?

A.

Storage (S)

B.

Business (B)

C.

Mercantile (M)

Full Access
Question # 45

An owner wants to control the lights above the television separately from the lights over the table in their conference room. What should the designer do?

A.

Add an additional switch zone

B.

Change the switches to three-way switches

C.

Gang the switches under a single switch plate cover

D.

Control the lights over the table with an occupancy sensor

Full Access
Question # 46

The project team is reviewing a mock-up of a faux plaster ceiling finish. The mock-up is a 4'x4' board on an easel in the contractor’s construction trailer. What should the designer request?

A.

A larger mock-up with the adjacent wall and light fixture finishes

B.

Three mock-ups with different shades of plaster and softer ambient lighting

C.

To view the sample horizontally from below and with lighting similar to the design

Full Access
Question # 47

A building owner hires a design firm to renovate an existing office suite into a live-work space. What is the FIRST step the designer should take?

A.

Perform a site visit

B.

Confirm zoning ordinance

C.

Document the project drivers

D.

Verify the building construction type

Full Access
Question # 48

Information regarding product substitutions is found in the

A.

bid (tender) forms

B.

general requirements

C.

material specifications

Full Access
Question # 49

What is the MAXIMUM occupant load of a business occupancy with one exit?

A.

49

B.

50

C.

69

D.

70

Full Access
Question # 50

Where open risers are permitted in a commercial space, what is the MAXIMUM clear space between risers?

A.

3" [76 mm]

B.

4" [102 mm]

C.

7" [178 mm]

D.

11" [279 mm]

Full Access
Question # 51

Earthquakes and the loads caused by winds are examples of

A.

Live loads

B.

Dead loads

C.

Static loads

D.

Dynamic loads

Full Access
Question # 52

What core information should be captured in the design contract to demonstrate a clear understanding of the physical parameters of the project?

A.

Property address, usable square footage [m²], and projected use

B.

Room name, client, and occupant load

C.

Room measurements, drawing references, and furniture requirements

D.

Occupant load, circulation ratio, and building classification

Full Access