Summer Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

What are the benefits of using the benchmarking option of the DMO for SUM? Note There are 2 correct answers to this question

A.

You can verify that the content of the download directory matches the stack XML file.

B.

You can obtain migration duration tiles from a previous benchmark run that can be used to optimize the next runs

C.

You can record the modification adjustment during migration and use the transports in the next runs.

D.

You can find the optimal number of parallel H3load processes by monitoring host performance

Full Access
Question # 5

You have chosen the "Advanced" option during the main configuration of the SUM tool. Which steps take place via the shadow instance?

There are 2 correct answers to this question.

Response:

A.

Conversion of application tables (PARCONV_UPG)

B.

Activation of dictionary objects (ACT_UPG)

C.

Switch to new repository (EU_SWITCH)

D.

Modification adjustment (SPDD)

Full Access
Question # 6

In which case can you use near-Zero Downtime Maintenance (nZDM)? Note: There are 2 correct answers to this question.

A.

When performing an SAP S/4HANA conversion with DMO

B.

When performing an SAP S/4HANA conversion without u DMO

C.

When upgrading an SAP S/4HANA Server system

D.

When upgrading an SAP ECC system with DMO

Full Access
Question # 7

What do you do to prepare the database migration option of a SUM procedure?

There are 3 correct answers

Response:

A.

Extract the SAP HANA database installation archive

B.

Move the stack.xml update file into the download folder

C.

Extract the SAP HANA client installation archive

D.

Move the SAPM update archive into the download folder

E.

Move the R3trans update archive into the download folder

Full Access
Question # 8

During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison?

Please choose the correct answer.

Response:

A.

It performs a comparison on selected tables using check sum.

B.

It performs a comparison on all tables using row counts.

C.

It performs a comparison of all tables using check sum.

D.

It does NOT perform any table comparison.

Full Access
Question # 9

You want to perform custom code check via ABAP test cockpit in preparation of your SAP S/4HANA conversion? What kind of SAP System can you use to generate the custom code migration worklist?

A.

AA

B.

A Standalone SAP system with ABAP 7.51 or above

C.

An SAP S4HANA 1709 sandbox system

Full Access
Question # 10

You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".

Where can you change this during the migration via the Utilities option of the SUM UI?

There are 2 correct answers to this question

Response:

A.

In SUM Phaselist

B.

In Process Control Center

C.

In SUM Parameters

D.

In DMO Migration Preparation

Full Access
Question # 11

What is the different between the benchmaking and the repetition option of the Database Migration Option (DMO) of SUM?

A.

The benchmaking option allows you to migration a specified set of tables

B.

The benchmaking option allows you to repeat the uptime migration

C.

The repetition option allows you to run the migration without a shadow system

D.

The repetition option allows you to repeat the complete migration

Full Access
Question # 12

In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?

There are 2 correct answers to this question.

Response:

A.

Upgrading to SAP ECC 6.08 without using DMO

B.

Using DMO when applying Support Packages to SAP ECC 6.07

C.

SAP S/4HANA conversion to SAP S/4HANA 1709

D.

Updating to SAP ECC 6.07 using DMO

Full Access
Question # 13

In which part of an upgrade does SUM allow you to generate ABAP loads (SGEN)?

There are 2 correct answers to this question.

A.

During downtime

B.

During SPDD

C.

Post-downtime

D.

During uptime

Full Access
Question # 14

SUM was registered at the SAP Host Agent. Based on which information does the SAP Host Agent determine the path to the SUM directory.

A.

The path was stored in file host_profile during registration

B.

The path was stored to the environment of user adm during registration

C.

The path is taken from the URL entered in the browser to start SUM

D.

The path was stored in file sumabap conf during registration

Full Access
Question # 15

Which maintenance events are possible with SUM for an SAP system based on AS ABAP 7.40 and above? There are 3 correct answers to this question.

A.

Dual Stack split

B.

Support Package Stack update

C.

Database migration

D.

Release upgrade

E.

Homogenous system copy

Full Access
Question # 16

You are performing an SAP S/4HANA conversion. Which phases are executed during SUM technical downtime? Note: There are 2 correct answers to this question

A.

PARMVNT_UPG

B.

TABIMJJPG

C.

PARDIST_SHD

D.

TABIM_SHADOW_*

Full Access
Question # 17

You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.

A.

Software update

B.

Conversion

C.

Main import

D.

Migration

Full Access
Question # 18

Which circumstances will allow SUM to run without the creation of a shadow system?

Please choose the correct answer.

Response:

A.

Using the main configuration option "Single System" when installing an Add-On

B.

Using the main configuration option "Single System" in case of an upgrade.

C.

Using the database migration option (DMO) for SUM

D.

Using the main configuration option "Standard" when applying SAP Support Packages

Full Access
Question # 19

You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?

Please choose the correct answer.

Response:

A.

/ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)

B.

/ASU/SSM (ASU Simple Schedule Manager)

C.

/ASU/SHOW_NOTE (Show SAP Note via Web-Browser)

D.

/ASU/START (Start ASU Toolbox)

Full Access
Question # 20

You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. You have chosen table count verification, but not table contents comparison.

Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel.

Why are 40 Process Buckets executed in parallel?

A.

These are 40 pairs of Reload processes, so there are 80 R3load processes running.

B.

SUM is still running in uptime; the 40 defined Reload processes are considered.

C.

Without table contents comparison, only 40 R3load processes are being started.

D.

There are 40 Reload processes used for copying and 40 Reload processes for table count verification.

Full Access
Question # 21

Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

A.

Shadow on target creation

B.

Downtime conversion

C.

Silent data migration (SDM)

D.

Downtime migration

Full Access
Question # 22

During a DMO procedure with SUM, after which phase is the repository first available on the target database?

Please choose the correct answer.

Response:

A.

Uptime migration (EU_CLONE_MIG_UT_RUN)

B.

ParaUel distribution (PARDIST_SHD)

C.

Downtime migration (EU_CLONE_MIG_DT_RUN)

D.

Shadow repository creation (EU_IMPORT*)

Full Access
Question # 23

Which steps can SUM perform during an SAP S/4HANA conversion? Note; There are 2 correct answers to this question.

A.

Unicode conversion

B.

Custom code analysis

C.

Database migration

D.

Software update

Full Access
Question # 24

You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?

Please choose the correct answer.

Response:

A.

Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.

B.

Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU &UC) procedure.

C.

Perform the Unicode conversion before the upgrade to SAP ECC 6.08.

D.

Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.

Full Access