Black Friday Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?

A.

10,586

B.

9,280

C.

9,559

D.

10,278

Full Access
Question # 5

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

Marketing has determined that XY2 can safely increase their per unit selling price to SO.55. The new break even amount for sales (in units) based on the new contribution margin is:

A.

40,000 units

B.

6,000 units

C.

50,000 units

D.

60,000 units

Full Access
Question # 6

The written word is often more useful than the spoken. Guidelines for writing include:

A.

Use short sentences; use short words; avoid jargon and abbreviations; use complete sentences; stick to one idea per paragraph; have a beginning, middle and end; be accurate

B.

Organize the background information; state the problem list the options or alternatives; state the recommendation (s); conclude and summarize with why the recommendation is the best way to proceed

C.

Follow an outline; allow some time for "cooling" after compiling the draft before revising; when revising, allow plenty of time for several sessions

D.

Explain, report, describe, clarify, define and demonstrate

Full Access
Question # 7

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.150 from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses.

Using normally accepted engineering economic practices, what are the two expected methods that should be used to determine the capital recovery costs for the new press?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 8

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Full Access
Question # 9

Which of the following best describes the three key participants for projects that are executed under a three-party contractual relationship?

A.

Contracting officer, contractor, and contractor project manager

B.

Procurement officer, underwriter, and project manager

C.

Owner, engineer, contractor

D.

Client, project manager, procurement manager

Full Access
Question # 10

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

Full Access
Question # 11

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Full Access
Question # 12

____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.

A.

Soft logic

B.

Hard logic

C.

Deductive logic

D.

Inductive logic

Full Access
Question # 13

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Based on the information provided, which statement is most correct?

A.

The truck should be leased

B.

The truck should be purchased

C.

The truck should not be leased

D.

The truck should not be purchased

Full Access
Question # 14

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Full Access
Question # 15

A work breakdown structure (WBS) is developed because:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Full Access
Question # 16

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, copper prices will have increased by what percentage over today's price?

A.

4.6%

B.

3.5%

C.

6.6%

D.

2.5%

Full Access
Question # 17

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be?

A.

$16,380

B.

$16,578

C.

$15,937

D.

$16,273

Full Access
Question # 18

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return?

A.

10.4%

B.

9.1%

C.

8.3%

D.

9.9%

Full Access
Question # 19

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs amounting to $55.00/unit?

A.

22.22%

B.

$55.00

C.

2

D.

338.5

Full Access
Question # 20

Deliberate low bidding is often referred to as buying the job. Which of the following would not be a reason for low bidding?

A.

Survival

B.

Backing out of the bid competition

C.

Reducing cm eliminating competition

D.

Detecting significant errors in the purchaser's request for quote

Full Access
Question # 21

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Full Access
Question # 22

A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?

A.

3.0 cubic yards

B.

2.0 cubic yards

C.

3.5 cubic yards

D.

2.5 cubic yards

Full Access
Question # 23

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Full Access
Question # 24

Meetings require:

A.

Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the total physical and human setting of the meeting

B.

Goals, an agenda, preparation, conclusions, control and conversations that are relevant

C.

Goals, an agenda, preparation, control, good listening skills and relevant discussions

D.

Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where appropriate

Full Access
Question # 25

A schedule's late dates are calculated during the:

A.

Loop calculations

B.

Backward pass

C.

Forward pass

D.

Float

Full Access
Question # 26

The process of stating goals and determining the most effective way of reaching them is the definition for:

A.

Implementing

B.

Mission Statement

C.

Managing

D.

Planning

Full Access
Question # 27

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

A.

Total float

B.

Remaining duration

C.

Free float

D.

Just-in-time scheduling

Full Access
Question # 28

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The value of the truck at the end of year five (5) would be:

A.

$0

B.

$14,265

C.

$25,000

D.

$23,366

Full Access
Question # 29

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Calculate the mean unit cost.

A.

$48.09

B.

$48.22

C.

$48.35

D.

$46.59

Full Access
Question # 30

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

What is the range of unit costs?

A.

$21.57

B.

$26.65

C.

$48.22

D.

$485.00

Full Access
Question # 31

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Resource planning must take all of the following into account except:

A.

Types of materials, equipment and labor skills required to complete the project

B.

Cash flow (expenditures) limitations for completing work on the project

C.

Time available to complete the project

D.

Earned value techniques established for the project

Full Access
Question # 32

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Present worth calculations is represented by which of the following equations?

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 33

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

A.

Liability insurance

B.

Performance bond

C.

Bid bond

D.

Surety bond

Full Access
Question # 34

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

A.

Recalculate the early finish for each activity

B.

Recalculate the early start for each activity

C.

Update the remaining duration for each activity

D.

Recalculate the critical path

Full Access
Question # 35

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

It S480 is the target net profit, then the total sales volume (in dollars) is:

A.

$30,000

B.

$37,500

C.

$34,400

D.

$32,400

Full Access
Question # 36

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following statements is correct?

A.

The graph of a normal curve is bell-shaped and is symmetrical about the standard deviation.

B.

The graph of a normal curve is bell-shaped and is symmetrical about the variance.

C.

Some graphic methods for describing quantitative data ate histograms and frequency distribution.

D.

Some graphic methods for describing qualitative data are histograms and frequency distribution.

Full Access
Question # 37

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the range of estimated quantities?

A.

$26.78 to $75.00

B.

$485

C.

$45 to $530

D.

$48.22

Full Access
Question # 38

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is invested now at 10% compounded annually, what will the investments be worth 10 years from now?

A.

$25,940

B.

$29,450

C.

$21,345

D.

$16,180

Full Access
Question # 39

A task has an early start of day 4. late start of day 14. early finish of day 10. and a late finish of day 20. What is the task's float?

A.

4

B.

10

C.

20

D.

9

Full Access
Question # 40

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

A reason for using a Construction Manager type agreement is:

A.

To better coordinate contractors

B.

Coordinate the owner and engineer as in Type A

C.

To better coordinate subcontractors

D.

To better coordinate contractors and subcontractors as in Type B

Full Access
Question # 41

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs from Atlanta, GA?

A.

$40.59

B.

3

C.

$48.33

D.

33.33%

Full Access
Question # 42

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Full Access
Question # 43

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above

B.

Bid unit rate, owner quantities are within estimate range

C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range

D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range

Full Access
Question # 44

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Full Access
Question # 45

AACE International defines_____________as the primary activity that separates Value Methodology (VM) from other "improvement" practices and has the objective

to develop the most beneficial areas for continuing study.

A.

Not present worth method

B.

Benefit/Cost ratio (B/C) method

C.

Function Analysis Phase

D.

Life cycle costs method (LCC)

Full Access
Question # 46

A _________contract allows the contractor to freely employ whatever methods and resources it chooses in order to complete the work.

A.

Guaranteed maximum price

B.

Cost reimbursable/Fixed fee

C.

Measured unit price

D.

Lump-sum/Fixed price

Full Access
Question # 47

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

When analyzing a precedence diagram schedule, the "backward pass"

A.

Allows total float to be calculated

B.

Determines the duration of each activity

C.

Calculates the earliest allowable start and finish times for the activities in the schedule

D.

Allows activities to finish as soon as all their 'predecessor' relationships are satisfied

Full Access
Question # 48

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?

A.

Continuous compounding rate

B.

Simple interest rate

C.

Minimum attractive rate of return

D.

Nominal interest rate

Full Access
Question # 49

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

Full Access
Question # 50

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Depreciation (in the United States) is calculated in accordance with which of the following?

A.

Modified Accelerated Cost Recovery System (MACRS)

B.

The Federal IRS Reform Act (FIRSRA)

C.

Generally Accepted Accounting Practices (GAAP)

D.

Accelerated Cost Recovery System (ACRS)

Full Access
Question # 51

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual estimated tax would be:

A.

$3,869

B.

$5,565

C.

$10,500

D.

$11,925

Full Access
Question # 52

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%?

A.

$289,370

B.

$318,740

C.

$265,798

D.

$420,236

Full Access
Question # 53

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?

A.

Schedule is good, cost is bad

B.

Schedule is good cost is good

C.

Schedule is bad cost is good

D.

Schedule is bad, cost is bad

Full Access
Question # 54

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?

A.

Belonging needs

B.

Safety needs

C.

Power needs

D.

Self-actualization

Full Access
Question # 55

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

Full Access
Question # 56

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

A.

For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.

B.

For changes in construction cost 'or varied works carried out beyond the original dale of completion

C.

In no situation

D.

For changes in The cost of resources beyond the control of either party

Full Access