Weekend Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Full Access
Question # 5

Which of the following risk management processes uses brainstorming as a technique?

A.

Identify Risks

B.

Monitor and Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 6

What process determines which risks might affect the project?

A.

Qualitative risk analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Quantitative risk analysis

Full Access
Question # 7

What are three basic types of project phase-to-phase relationships?

A.

Sequential, Overlapping, Non-overlapping

B.

Sequential, Iterative, Overlapping

C.

Sequential, Non-overlapping, Iterative

D.

Iterative, Overlapping, Non-overlapping

Full Access
Question # 8

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Full Access
Question # 9

The project management processes presented in the PMBOK Guide should:

A.

Always be applied uniformly

B.

Be selected as appropriate by the sponsor

C.

Be selected as appropriate by the project team

D.

Be applied based on ISO guidelines.

Full Access
Question # 10

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Full Access
Question # 11

Which of the following is an output of the Estimate Activity Resources process?

A.

Alternative analysis

B.

Bottom-up estimating

C.

Resource breakdown structure

D.

Enterprise environmental factors

Full Access
Question # 12

What is the term assigned to products or services having the same functional use but different technical characteristics?

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Full Access
Question # 13

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Full Access
Question # 14

Which of the following describes the purpose of the quality control process?

A.

To identify quality requirements of the project

B.

To identify ineffective processes and eliminate them

C.

To assess performance and recommend necessary changes

D.

To ensure quality standards are used

Full Access
Question # 15

What is a tool to improve team performance?

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-Location

Full Access
Question # 16

Which of these are logical dependencies in a precedence diagram method?

A.

End-to-end

B.

Finish-to-end

C.

Start-to-end

D.

Start-to-start

Full Access
Question # 17

Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Quality Planning

D.

Performance Reporting

Full Access
Question # 18

In which of the following team development stages does the team meet and learn about the project and their formal roles and responsibilities?

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Full Access
Question # 19

Which process group typically consumes the bulk of a project's budget?

A.

Monitoring & Controlling

B.

Executing

C.

Planning

D.

Initiating

Full Access
Question # 20

During the initial stages of the project, what do activity attributes include?

A.

Activity name, dependencies, assumptions

B.

Activity ID, WBS ID, activity name

C.

Activity ID, assumptions, constraints

D.

Activity name, WBS ID, activity description

Full Access
Question # 21

A project manager needs the project team to make a group decision. Which of the following is a method that can be used to reach a group decision?

A.

Expert judgment

B.

Majority

C.

SWOT analysis

D.

Brainstorming

Full Access
Question # 22

Company A is delivering a product in three parts. The contract allows for the parts to be delivered either one after the other or at the same time.

Which type of project phasing will allow for the most flexibility in delivering the full product when product requirements are subject to rapid change?

A.

Sequencing the delivery phases one after the other

B.

Overlapping the delivery phases

C.

Delivering the products iteratively

D.

Delivering all of the product at the same time

Full Access
Question # 23

A Trend Analysis is best described as:

A.

Examining project performance over time

B.

Calculating Earned Value

C.

Calculating Cost Variance

D.

Analyzing performance of similar projects over time

Full Access
Question # 24

Stakeholder influence is greatest at the ______ of the project.

A.

Beginning

B.

Closing

C.

Controlling

D.

Executing

Full Access
Question # 25

Which is not included in Performance improvements :

A.

Improvements in amount of overtime worked

B.

Improvements in individual skills

C.

Improvements in team behaviours

D.

Improvements in team capabilities

Full Access
Question # 26

Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.

A.

Progressive elaboration

B.

Stake holder's review

C.

p'an project life cycle

D.

Fast backing

Full Access
Question # 27

Which of the following is ensuring that all features and functions are included in a product or service

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope

Full Access
Question # 28

The project management plan:

A.

Identifies all the steps and processes that will be used after a project is initiated

B.

Steps needed to complete a project task

C.

Prepared at the beginning and fixed throughout the execution of the project

D.

Includes project charter

Full Access
Question # 29

Which of the following is NOT an example of a type of schedule report?

A.

Gantt chart

B.

Milestone chart

C.

fishbone diagram

D.

network diagram

Full Access
Question # 30

Which process must occur after a project manager has been assigned to the project?

A.

Collect Requirements

B.

Develop the project charter

C.

Develop the project statement of work

D.

Develop project closing document

Full Access
Question # 31

When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

A.

Parametric estimating

B.

Bottom-up estimating

C.

Top-down estimating

D.

Analogous estimating

Full Access
Question # 32

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

A.

Schedule Control

B.

Activity Definition

C.

Schedule Development

D.

Activity Resource Estimating

Full Access
Question # 33

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

A.

$600

B.

$1200

C.

$3000

D.

$100

Full Access
Question # 34

In an optimal organization structure, the project manager is:

A.

Functional

B.

Weak matrix

C.

Piojectized

D.

Dedicated project team

Full Access
Question # 35

The scope management provides:

A.

A basis for future decisions about the project.

B.

A baseline to accomplish verification measures.

C.

A baseline to evaluate potential scope changes.

D.

All of the above.

Full Access
Question # 36

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

A.

Create WBS

B.

Vei*

C.

Value analysis

D.

Control Scope

Full Access
Question # 37

Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?

A.

Precedence Diagramming Method (PDM)

B.

Gant Cnart Diagram (GCD)

C.

Dependency Diagramming Method (DDM)

D.

Arrow Diagramming Method (ADM)

Full Access
Question # 38

Your project team is composed of team members in three countries plus a contractor team in a fourth country. What tool would optimize communication?

A.

Extranet-based electronic document repository

B.

Manual filing system

C.

War loom

D.

Verbal

Full Access
Question # 39

Which of the following best describes project scope?

A.

The work that must be done in order to deliver a product with the specified features and functions

B.

The description of the project deliverables

C.

The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks

D.

The process of planning and executing all of the required work to deliver the project

Full Access
Question # 40

Which of the following is NOT an input of Estimate Costs?

A.

Earn Value Analysis

B.

Scope Baseline

C.

P'sk Register

D.

Human Resource Plan

Full Access
Question # 41

A Change Control Board should be _______?

A.

flexible

B.

Include the project manager

C.

appropriate authority

D.

al1 of the above

Full Access
Question # 42

Which of the following is an output of Define Scope?

A.

PBS

B.

Project Scope statement

C.

WBS Template

D.

Constraints

Full Access
Question # 43

A Project Cost Management plan is created as a part of:

A.

Develop Project Management Plan process

B.

Control Costs process

C.

Determine Budget process

D.

Estimate Costs process

Full Access
Question # 44

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:

A.

Enterprise benefits measurement methods when selecting a project

B.

Integral parts of the SOW

C.

Ways to ensure stakeholder commitment

D.

Project selection methods

Full Access
Question # 45

What is the purpose of the WBS?

A.

To show which work elements have been assigned to organizational units.

B.

To ensure that all work within a project is identified and defined within a common framework.

C.

To show the organizational structure of a program.

D.

all of the above

Full Access
Question # 46

How many communication channels will be required in a project in which 10 individual are participating?

A.

45

B.

12

C.

10

D.

5

Full Access
Question # 47

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Full Access
Question # 48

Adjusting Leads and Lags is a technique for:

A.

Develop Schedule

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Full Access
Question # 49

Which of the following is a tool and technique for activity duration estimating?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Top-down estimating

D.

Bottom-up estimating

Full Access
Question # 50

Which of the following is TRUE about most project life cycles?

A.

Staffing level is highest at the start.

B.

The stakeholders' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Full Access
Question # 51

EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?

A.

EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]

B.

EAC = BAC - AC

C.

EAC = 1 - CPI

D.

EAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]

Full Access
Question # 52

Expected Monetary Value (EMV) analysis is commonly used in:

A.

probability distribution.

B.

decision tree diagram.

C.

sensitivity analysis.

D.

modeling and simulation.

Full Access
Question # 53

Assumptions are factors that, for planning purposes, are considered to be ______.

A.

True, real, or certain

B.

True, real, or uncertain

C.

Real

D.

Verbal

Full Access
Question # 54

Project just went into inclusion mode. This means that project __________.

A.

Has become part of the business processes

B.

Has been accepted by the sponsor and the client

C.

Will be closed due to lack of resources

D.

None of the above

Full Access
Question # 55

Which of the following is conflict resolution technique?

A.

Compromise

B.

Smoothing

C.

Foimal

D.

Coercive

Full Access
Question # 56

__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.

A.

Rolling wave planning

B.

Progressive elaboration

C.

Milestone detail planning

D.

Expert judgment

Full Access
Question # 57

You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

A.

Save the old versions

B.

No need to save old version

C.

Scrap the old version

D.

Old version is not required

Full Access
Question # 58

The main purpose of project initiation is to ________.

A.

Assign the project manager to the project

B.

Formally describe the project

C.

Produce the project charter

D.

Formally authorize the project

Full Access
Question # 59

You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?

A.

Social need

B.

Physical need

C.

Safety and security

D.

Security

Full Access
Question # 60

______________ provides details about how the project scope may be changed.

A.

Control Scope system

B.

VeiirV Scope

C.

Scope Charter

D.

Scope Management plan

Full Access
Question # 61

A requirement document is an input of __________ process?

A.

Collect Requirements

B.

Define Scope

C.

Integrated Change Control

D.

Monitor and Control Project Work

Full Access
Question # 62

What is a corrective action?

A.

An action that brings future project events Into alignment with the project plan

B.

An action to correct something in the project

C.

An action to prevent something in the project

D.

Corrective action is not related to project

Full Access
Question # 63

Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.

A.

Initiation Process

B.

Project closer Process

C.

Estimation Process

D.

Closing process

Full Access
Question # 64

Delivery dates and availability of resources can be found in the details of the __________.

A.

Work Breakdown Structure

B.

sow

C.

Project Charter

D.

Project Scope Statement

Full Access
Question # 65

Which risk response is most likely to involve contingency reserves?

A.

Acceptance

B.

shaie

C.

Mitigate

D.

Transfer

Full Access
Question # 66

Which of the following does not provided by scope statement?

A.

Project justification

B.

Project product

C.

Project manager authority

D.

Project objective

Full Access
Question # 67

How many communication channels will be required in a project in which 5 individual are participating?

A.

10

B.

12

C.

4

D.

5

Full Access
Question # 68

Which one of the following is not an output of contract closure?

A.

close contracts

B.

Lessons learned documentation

C.

Deliverable acceptance

D.

Scope statement

Full Access
Question # 69

Who applies project selection methods to decide whether to accept or reject a project?

A.

Project sponsor

B.

Project team

C.

Project manager

D.

Senior Management

Full Access
Question # 70

Which one of the following comes first in the project plan?

A.

Scope Statement

B.

Quality Plan

C.

WBS

D.

Development Plan

Full Access
Question # 71

Which of the following activities is not part of Plan Risk Management?

A.

Updating risk register

B.

Determining risk roles and responsibilities

C.

Identifying risk categories

D.

Developing a risk management plan

Full Access
Question # 72

Which of the following is an output of Verify Scope?

A.

Formal acceptance

B.

WBS template

C.

sow acceptance

D.

Rework

Full Access
Question # 73

Which document formally authorizes a project?

A.

The project charter

B.

Project scope statement

C.

The P'oject contract

D.

Project closing document

Full Access
Question # 74

Project Quality Management includes:

A.

Customer satisfaction

B.

Prevention over inspection

C.

Continuous improvement

D.

Al1 of the above

Full Access
Question # 75

The project baseline is _______.

A.

Original plans plus the approved changes

B.

Important in the project initiation phase

C.

Initial estimates for tasks and resource utilization

D.

Original plans and the approved major changes

Full Access
Question # 76

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

A.

Procurement Management

B.

Planning Management

C.

Scope Management

D.

Control Management

Full Access
Question # 77

You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?

A.

Weighting system

B.

Screening system

C.

Seller rating system

D.

Expert judgment

Full Access
Question # 78

The product description of a project can help to create procurement details. Which one of the following best describes product description?

A.

The product description defines the contracted work, based on the requirements of the project customer

B.

The product description defines the contracted work

C.

The product description defines the requirements for the contract work

D.

Al1 of the above

Full Access