Weekend Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.

A.

The order lot size is NOT within the validity range of a production version.

B.

NO production lines are assigned to the production versions.

C.

All production versions for the material are locked.

D.

NO bills of material (BOMs) are assigned to the production versions.

Full Access
Question # 5

What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

Quantity

B.

Status

C.

Installation point

D.

Scrap percentage

Full Access
Question # 6

What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?

A.

MRP creates a dependent requirement.

B.

A sales order is delivered.

C.

MRP creates a planned order.

D.

A sales order is created.

Full Access
Question # 7

What does forecasting in the dem planning cycle include? Note: There are 3 correct answers to this question.

A.

Oneoff events

B.

Past production planning quantities

C.

Past quotation quantities

D.

Market intelligence

E.

Past sales order quantities

Full Access
Question # 8

What are the key features of using a low level code? Note: There are 2 correct answers to this question.

A.

To determine the priority of alternative components inside ATP

B.

To determine how costs are rolled up by product costing

C.

To determine the sequence in which materials are planned in MRP

D.

To determine the use of subitems inside material BOM (bill of material)

Full Access
Question # 9

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

A.

Work center

B.

Material master

C.

Routing

D.

Production version

Full Access
Question # 10

In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

A.

Use a specific MRP list.

B.

Use a specific material status.

C.

Use a specific material group.

D.

Use a specific MRP type.

Full Access
Question # 11

You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received.Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Production by lot size (30)

D.

Planning at assembly level (70)

Full Access
Question # 12

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

A.

You can reschedule the operation using lead time scheduling.

B.

You can reschedule the operation using infinite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Full Access
Question # 13

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched.

How does the insertion take place?

A.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

B.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

C.

The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

D.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward.

Full Access
Question # 14

You are a consultant on an SAP S/4HANA Cloud Greenfield project.

Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.

A.

Efficiency

B.

Accuracy

C.

Timeliness

D.

Stability

Full Access
Question # 15

What are the advantages of collective orders? Note: There are 2 correct answers to this question.

A.

To perform availability checks across the entire collective order

B.

To coordinate orders in the planning board for a collective order

C.

To show the flow of batches across the entire collective order

D.

To post confirmations for the entire collective order

Full Access
Question # 16

Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

In which storage location is the BOM required?

B.

Is the material type allowed in the BOM?

C.

Which base unit of measure does the material have?

D.

What status does the BOM have?

Full Access
Question # 17

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

A.

Production cost collector

B.

Production version

C.

Repetitive manufacturing profile

D.

Routing

Full Access
Question # 18

You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

A.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.

B.

Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.

D.

Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.

Full Access
Question # 19

What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation? Note: There are 2 correct answers to this question.

A.

Scheduling of an operation takes place as close as possible to the desired date.

B.

Sequencing on multiactivity resources is automatically updated.

C.

Neighboring operations can be moved in both directions in order to create a slot.

D.

Changes are automatically implemented in the complete collective order.

Full Access
Question # 20

Your project uses process orders for the production of liquid chemicals.

What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.

A.

Resource hierarchy

B.

Resource selection

C.

Resource matrix

D.

Resource network

Full Access
Question # 21

How would you define pegging in the context of Advanced Planning?

A.

An evaluation that is ordered according to the billofmaterial structure of all related products represents the relationship between the receipt the issue elements

B.

An evaluation to identify overstock situations in the balance between the receipt the issue elements after the production planning run

C.

An evaluation that is ordered according to the network structure of all related products represents the coverage of issue elements with receipt elements stock

D.

An evaluation to identify material or capacity shortages in the billofmaterial structure after the production planning run

Full Access
Question # 22

You have maintained the parameters for simple discontinuation in the material master of a component.

Which business process will be affected if the available stock is zero the discontinuation date is in the past?

A.

Back flushing

B.

Kanban

C.

Material requirements planning

D.

Production order release

Full Access
Question # 23

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Full Access
Question # 24

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

A.

When several operations are maintained for one product

B.

When alternative resources are used within one operation

C.

When several production versions are maintained for one product

D.

When multiple planned orders are scheduled in parallel on one resource

Full Access