How can you set up the supply source for the Kanban process in SAP S/4HANA?
Note: There are 3 correct answers to this question.
Which time elements can be reduced by a reduction strategy?
Note: There are 3 correct answers to this question.
which actions does the system perform by default when you save a confirmation for a finished
product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Note: There are 2 correct answers to this question
What could be the reason for different combinations of components in a multiple bill of
material (BOM)?
Note: There are 2 correct answers to this question.
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.
Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?
Which of the following elements does MRP take into account during net requirement
calculation? Note:
There are 2 correct answers to this question.
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.
Note: there are 2 correct answers to this question.
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.