Summer Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

What can you use heuristics in Advanced Planning (PP/DS) for?

A.

To optimize costs and times in production plans

B.

To solve planning problems for defined objects

C.

To automate material movements in material staging

D.

To set default values in production master data

Full Access
Question # 5

How can you set up the supply source for the Kanban process in SAP S/4HANA?

Note: There are 3 correct answers to this question.

A.

Use stock transfer reservations for stock transfer.

B.

Use purchase orders for external procurement.

C.

Use quotations for internal and external procurement

D.

Use run schedule quantities for in-house production.

E.

Use purchasing costs for automated source prioritization.

Full Access
Question # 6

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

Full Access
Question # 7

which actions does the system perform by default when you save a confirmation for a finished

product in repetitive manufacturing?

Note: There are 3 Correct answers to this question.

A.

Posting of production costs to the production cost collector

B.

posting of goods receipt for the product

C.

Reduction of associated capacity requirements

D.

Archiving of document for assembly scrap

E.

Material staging for next order in sequence

Full Access
Question # 8

Where do you maintain the work center that represents the production line for repetitive manufacturing?

Note: There are 2 correct answers to this question

A.

Production cost collector

B.

Repetitive manufacturing profile

C.

Routing

D.

Production version

Full Access
Question # 9

What could be the reason for different combinations of components in a multiple bill of

material (BOM)?

Note: There are 2 correct answers to this question.

A.

BOM header status

B.

Manufacturing date

C.

Lot size

D.

BOM item status

Full Access
Question # 10

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

A.

Queue

B.

Teardown time

C.

Move time

D.

Setup Time

Full Access
Question # 11

What data can you maintain in the subitems of a bill of material (BOM)?

Note: There are 2 correct answers to this question.

A.

Installation point

B.

Item type

C.

Quantity

D.

Scrap percentage

Full Access
Question # 12

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

A.

Routing

B.

Work Center

C.

Bill of material (BOM)

D.

Material Master

Full Access
Question # 13

which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?

A.

you can use mass processing to set production orders to technically complete

B.

you can use the production scheduling profile to automatically set orders toI technicallycomplete

C.

You can use trigger points to automatically create rework orders via confirmation.

D.

You can use mass processing to read PP master data for production orders

Full Access
Question # 14

How can a material availability check be triggered automatically for a production order?

Note: There are 2 correct answers to this question.

A.

By capacity planning

B.

By mass processing

C.

By order release

D.

By order confirmation

Full Access
Question # 15

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?

A.

The new operation is inserted at the desired time; the previous dispatched operation is moved forward.

B.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward

C.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

D.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

Full Access
Question # 16

Which of the following elements does MRP take into account during net requirement

calculation? Note:

There are 2 correct answers to this question.

A.

Forecast key figures

B.

Safety Stock

C.

Maximum stock level

D.

Purchase orders

Full Access
Question # 17

You want to create a production order. What methods can you use?

Note: There are 2 correct answers to this question.

A.

Create by order release

B.

Convert a purchase requisition

C.

Create in Kanban process

D.

Create without material

Full Access
Question # 18

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.

Full Access
Question # 19

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

A.

Order type

B.

Planning strategy

C.

Requirements profile

D.

Requirements type

Full Access
Question # 20

You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

A.

Manual Planning Without Check

B.

Consumption-Based Planning

C.

Material Requirements Planning

D.

Advanced Planning

Full Access
Question # 21

What is the difference between co-products and by-products?

A.

Only co-products are identified by a special item category in the bill of material (BOM)

B.

Only co-products can be manufactured in isolation from the main product

C.

Only co-products have a zero inventory valuation

D.

Only co-products appear in the process or production order settlement rule

Full Access
Question # 22

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.

Note: there are 2 correct answers to this question.

A.

Manual maintenance

B.

100% check

C.

First in First out (FIFO).

D.

Simultaneous

Full Access
Question # 23

Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.

what is the impact of this decision?

Note: there are 2 correct answers to this question

A.

Storage Location MRP areas are required for sales-orders-specific stock.

B.

Net requirement calculation is carried out for every sales order individually.

C.

Both the reduction of make-to-order stock and requirements occur on delivery

D.

Sales orders have to be ATP-confirmed (available-to-promise) to saved.

E.

Production orders are created with sales order reference.

Full Access
Question # 24

Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

A.

The same batch management level is used

B.

The same base unit of measure is used.

C.

The quantity and value updates are the same

D.

The same account category is used

Full Access