You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
What does forecasting in the dem planning cycle include? Note: There are 3 correct answers to this question.
What are the key features of using a low level code? Note: There are 2 correct answers to this question.
Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
In your plant MRP is activated.
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received.Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched.
How does the insertion take place?
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
What are the advantages of collective orders? Note: There are 2 correct answers to this question.
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation? Note: There are 2 correct answers to this question.
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.
You have maintained the parameters for simple discontinuation in the material master of a component.
Which business process will be affected if the available stock is zero the discontinuation date is in the past?
How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?