Question # 4

What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

A.

A delivery document type must be configured

B.

A sold to party is necessary

C.

A shipping point is necessary

D.

A sales order must be created in advance

Full Access
Question # 5

You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

A.

Requirements type

B.

Requirements class

C.

Item category

D.

Schedule line category

Full Access
Question # 6

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

A.

Only capacity requirements

B.

Forward

C.

Current date

D.

Backward

Full Access
Question # 7

You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

A.

The manual hierarchical revenue planning will be displayed only if expert mode is activated

B.

The manual hierarchical revenue planning has no reference to cost elements

C.

Cost element reports can display costs but not revenues

D.

Cost element reports display integrated planning only

Full Access
Question # 8

What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question

A.

Settlement

B.

Milestone trend analysis

C.

Confirmations

D.

Progress analysis

E.

Results analysis

Full Access
Question # 9

Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question

A.

Sales order

B.

Billing

C.

Quotation

D.

Inquiry

Full Access
Question # 10

Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

A.

Document information records

B.

Internally processed activities

C.

Basic dates for activities

D.

Material components

E.

Relationships

Full Access
Question # 11

Resources

How are capacity requirements determined?

A.

Independent of scheduling and according to the capacity planner group.

B.

Using scheduling and the capacity category.

C.

Using the control key of an activity.

D.

Using scheduling and distribution key.

Full Access
Question # 12

You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

A.

Activity

B.

Network header

C.

Milestone

D.

Activity element

Full Access
Question # 13

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

A.

Float time can be negative

B.

Activities with the time constraint "Must start on" always have a negative float time

C.

The float time of WBS elements is calculated by extrapolation

D.

By default, critical activities have a float time, which is less than or equal to zero

E.

The maximum size of a free float is as large as the total float of an activity

Full Access
Question # 14

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the

project.

What are the prerequisites?

Note: There are 3 correct answers to this question

A.

A bill of material with sales views

B.

A material master with sales views

C.

Assignment between material and standard network

D.

Standard network with activities

E.

A production order

Full Access
Question # 15

You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

A.

Unit costing for WBS

B.

Easy Cost Planning (ECP) for WBS

C.

Detailed planning for WBS

D.

Planning of overall values

Full Access
Question # 16

Project Structure

You plan double the work on each internal activity for multiple project. What do you recommend?

A.

Use mass change (CNMASS) in the project system.

B.

Double the work of each internal activity, one after another, in the project Builder.

C.

Double the capacity in the work center.

D.

Use mass change within the project Builder (CJ20N).

Full Access