Winter Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

Which of the following can be derived automatically when you carry out scheduling in projects with networks?

There are 2 correct answers to this question.

Response:

A.

Activity dates

B.

WBS element dates

C.

Network dates

D.

Scheduling dates

Full Access
Question # 5

What is the transaction code for editing the planning profile?

Please choose the correct answer.

Response:

A.

OPSS

B.

OPDS

C.

OPSB

D.

OPSC

Full Access
Question # 6

An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?

Please choose the correct answer.

Response:

A.

Activity analysis tool

B.

Relationship analysis tool

C.

Cycle analysis tool

D.

Loop analysis tool

Full Access
Question # 7

Which of the following specifies how much time must elapse between individual archiving steps in network type?

Please choose the correct answer.

Response:

A.

Functional areas

B.

Residence times

C.

Classification indicator

D.

Functional areas

Full Access
Question # 8

Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders?

Please choose the correct answer.

Response:

A.

C

B.

B

C.

F

D.

E

Full Access
Question # 9

Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?

Please choose the correct answer.

Response:

A.

Progress analysis

B.

Cost forecasts

C.

Overhead costs

D.

Interest forecast

Full Access
Question # 10

Which of the following decides whether networks can be header assigned or activity-assigned?

There are 2 correct answers to this question.

Response:

A.

Order type

B.

Plant

C.

Billing type

D.

Network structure

Full Access
Question # 11

Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.

Which of the following costs can be planned?

There are 3 correct answers to this question.

Response:

A.

Cost element level

B.

Each material

C.

Each internal activity

D.

Internal service

Full Access
Question # 12

A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?

There are 2 correct answers to this question.

Response:

A.

Define Layout Detail Screen for WBS to specify customer-specific tabs.

B.

Define Create User-Defined Fields for WBS to specify the mandatory fields.

C.

Define Field Selection for WBS to specify the mandatory fields.

D.

Define Table Settings for WBS to specify customer-specific tabs.

Full Access
Question # 13

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

Response:

A.

The system status created is active.

B.

The system status master data locked is activate.

C.

You are not the responsible person for that WBS element.

D.

The confirmation exceeds the budget assigned to the WBS.

Full Access
Question # 14

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?

Please choose the correct answer.

Response:

A.

Contractual management

B.

Claim management

C.

Claim Planning

D.

Variance management

Full Access
Question # 15

You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...

There are 2 correct answers to this question.

Response:

A.

... basic dates of WBS elements are determined automatically.

B.

... the networks determine the schedule.

C.

... strict bottom-up planning is selected as the planning method.

D.

... forward scheduling is selected as the scheduling type.

E.

... the work breakdown structure determines the schedule.

Full Access
Question # 16

Which of the following master data fields of an internally processed activity have an impact on capacity requirements? Choose the correct answers (3)

A.

Usage

B.

Work

C.

Activity type

D.

Work center

E.

Duration

Full Access
Question # 17

In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?

Please choose the correct answer.

Response:

A.

Deactivate actual date consider indicator in Parameters for Network Scheduling.

B.

Deactivate the shift order indicator in Parameters for Network Scheduling.

C.

Activate the actual date consider indicator in Parameters for Network

Scheduling.

D.

Activate the shift order indicator in Parameters for Network Scheduling.

Full Access
Question # 18

Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?

There are 2 correct answers to this question.

Response:

A.

WBS elements

B.

Activities

C.

Milestones

D.

Structures

Full Access
Question # 19

Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?

Please choose the correct answer.

Response:

A.

Operative network

B.

Task network

C.

Standard network

D.

Internal network

Full Access
Question # 20

What do you choose when creating a new network by copying an operative network?

There are 3 correct answers to this question.

Response:

A.

PS texts

B.

Relationships

C.

Milestones

D.

WBS elements

Full Access
Question # 21

How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities?

Please choose the correct answer.

Response:

A.

Reduction

B.

Scheduling breech

C.

Milestones

D.

Capacity breech

Full Access
Question # 22

What are the different procurement types you can choose between if you choose direct procurement with item category N?

There are 2 correct answers to this question.

Response:

A.

Procurement for network

B.

Purchase requisition for network

C.

Purchase order for network

D.

Third-part order

Full Access
Question # 23

How can the capacity requirements of an activity be reduced?

There are 3 correct answers to this question.

Response:

A.

With partial confirmations of the activity

B.

By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)

C.

With the period-end closing

D.

By setting the status locked account assignment

E.

With the final confirmation of the activity

Full Access
Question # 24

Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response?

Please choose the correct answer.

Response:

A.

Budget plan

B.

Availability control

C.

Time horizon

D.

Tolerance limit

Full Access