Winter Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

Which of the following are search criteria In Resource Search in Project Management?

NOTE: There are 2correct answers to this question.

A.

Work centers

B.

Organizational units

C.

Qualifications

D.

plants

Full Access
Question # 5

What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?

NOTE: There are 3 correct answers to this question.

A.

Accounting integration for this project is active

B.

The project type must allow time recording with the CATS

C.

The role type must allow time recording with CATS

D.

The planned effortsis on the task

Full Access
Question # 6

The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.

What is the reason for the error message?

A.

The field service configuration of the item is missing

B.

The master switch for the interface settings for questionnaires it turned off

C.

The probability technical success field is configured as read only in the field control

D.

The field service configuration of the parent bucket of the item is missing

Full Access
Question # 7

Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?

NOTE: There are 3 correct answers to this question

A.

Phase

B.

Task

C.

Role

D.

Checklist item

Full Access
Question # 8

In project management, a WBS element for accounting integration was created automatically.

What is used to calculate the planned costs of this WBS element?

NOTE: There are 3 correct answers to this question

A.

Staffing of work in the role

B.

Duration planned on project tasks

C.

Demand planned on project roles

D.

Work planned on project task

Full Access
Question # 9

You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.

How do you make this selection available?

A.

Run a report to enable theconsultantrole type

B.

Assign theconsultantrole type to the appropriate project type

C.

Activate the consultant role type

D.

Assign the consultant role type to the appropriate item type

Full Access
Question # 10

You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.

What could be a reason for the system behavior?

A.

The role demand for the timeframe is too low

B.

The flexible Assignment indicator is active for the rile type in customizing

C.

The edit in parallel indicator is inactive for the role type in customizing

D.

The assigned effort for either of the resourceassignedis to high

Full Access
Question # 11

Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?

A.

Company code

B.

Controlling Area

C.

Cost Element

D.

Profit center

E.

CO Version

Full Access
Question # 12

You want to use a customer-specific status for items.

How do you configure the status in customizing?

A.

Create a business add-in (BAdi) for customer-specific status management

Activate the BAdi for the portfolio item type

B.

Create a status profile for the portfolio item objet type

Create the status within the status profile

Assign the status profile to a portfolio item type

C.

Create the status

Assign the status to a portfolio item type

Specify the status transitions with respect the portfolio item type

D.

Create the status and status transition within the portfolio type

Assign the portfolio item type to the portfolio type

Full Access