Weekend Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Full Access
Question # 5

What are two ways to associate milestone steps to tasks? (Choose two.)

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Full Access
Question # 6

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

A.

Assigned To

B.

Assignments

C.

Assigned

Full Access
Question # 7

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

A.

Estimated Date

B.

Projected Date

C.

Planned Date

Full Access
Question # 8

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Full Access
Question # 9

Which date type should an assignee update to change the completion date of a task?

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Full Access
Question # 10

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.

Actual Completion Date

B.

Progress Status

C.

Status

Full Access
Question # 11

A team lead wants to see all hours that have been logged this month by members of the team lead’s home team, organized by project. How should the team lead create this view?

A.

Navigate to a specific project and open the Hours tab. Filter the view by Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Repeat on all projects in which team members are assigned.

B.

Visit the Reports area and create a new Hour report. Add the filters for Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Group the results by Project > Name.

C.

Visit the Reports area and create a new Hour report. Add the filters for Hour > Entry Date > This Month and Project Status > Equal > Complete. Group the results by Project > Name.

D.

Visit the Teams landing page and on the Workload Balancer select the users' home team. Add the user filters for Task > Actual Start Date > This Month, click Apply. Update view settings and toggle on the Show remaining time setting.

Full Access
Question # 12

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Full Access
Question # 13

Which two statements are true about Groups and Teams? (Choose two.)

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Full Access
Question # 14

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

A.

Visit the Project page and create a new filter. Update the "Pending Approval" filter to "true" and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the "Pending Approval" filter to "true," and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to "tasks" and "issues." In the grouping tab, add a grouping for project name.

Full Access
Question # 15

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Full Access
Question # 16

What occurs when an individual enters a new commit date that is after the original planned date of a task?

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Full Access
Question # 17

How is the primary assignee of a task determined?

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Full Access
Question # 18

What parent object can have child objects?

A.

Issue

B.

Project

C.

Portfolio

Full Access
Question # 19

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?

A.

There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

B.

There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

C.

The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

Full Access
Question # 20

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

A.

Critical Path

B.

Baselines

C.

Milestones

Full Access
Question # 21

A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?

A.

Document

B.

Proof

C.

Approval

Full Access