Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
Which date type should an assignee update to change the completion date of a task?
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
A team lead wants to see all hours that have been logged this month by members of the team lead’s home team, organized by project. How should the team lead create this view?
A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.
What steps should the project manager take to create a custom Workfront report with this information?
A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?
What occurs when an individual enters a new commit date that is after the original planned date of a task?
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?
Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?
A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?