Black Friday Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

A manufacturing plant works in two shifts of eight hours each. A Manufacturing user wants four units of a work center resource, R1, to be available during nonworking time, outside the regular shift on a particularday.

Which is the correct sequence of steps to create a resource exception on the Manage Work Center Resource Calendar page?

A.

Click Inside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource dropdown list > Enter 4 in Default Units Available.

B.

Click inside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration Fields > Go to the Resource Availability region > Populate A units in the Default Availability column.

C.

Click outside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration fields > Go to the Resource Availability and Overrides region > Populate 4 units in the Availability Override column.

D.

Click outside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource drop-

Full Access
Question # 5

A manufacturing plant has two shifts of eight hours each for the work center WCI: day shift and night shift. You associate four units each of the resources R1, R2, R3, and R4 to WCI. The customer wants to assign ail units of R2 available for day and night shift.

What is the correct sequence of steps to achieve this?

A.

Associate R2 with WC1 > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 4in the Day Shift column > Enter 4 In the Night Shift column.

B.

Associate R2 with WC1> Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 4in the Day Shift column > Enter 4 In the Night Shift column.

C.

Associate R2 with WCI > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 in the Day Shift column > Enter 2 in the Night Shift column.

D.

Associate R2 with WCI > Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 In the Day Shift column > Enter 2 In the Night Shift column.

Full Access
Question # 6

A Plant Manager bought several machines for their ABC manufacturing plant. The plant is set up with a separate cost element set, ABC, in Manufacturing Cloud.

How must the Plant Manager configure these machines so that they are costed to the work order for which operations are performed on them?

A.

Set up the machines with a cost element type of "Resource" by selecting Cost Element Set Common.

B.

Set up the machines with a cost element type of "Overhead" by selecting Cost Element Set ABC.

C.

Set up the machines with a cost element type of "Resource" by selecting Cost Element Set ABC.

D.

Set up the machines with a cost element type of "Overhead" by selecting Cost Element Set Common.

Full Access
Question # 7

You create a work order, in which some of the operations have components with the Push supply type. While reporting material consumption on the Report Material Transaction page, you want the Push components to default whenever the operator selects Show Components.

Which setup task must you perform in the Manage Plant Parameters section to achieve this?

A.

Set Default Transaction Mode to Entered and Default Transaction Quantity to Work Definition.

B.

Set Default Transaction Mode to Work Definition.

C.

Set Default Transaction Mode to AIL

D.

Set Default Transaction Mode to Entered.

Full Access
Question # 8

To help ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), your client wants to enable audit trail for manufacturing work definitions and standard operations.

Which is NOT included in the audit trail for standard operations such as creation, update, and deletion?

A.

Work definition header and version attributes

B.

Descriptive flexfields (OFFs) at any level

C.

Item structure component attributes referenced from Product Information Management(PIM)

D.

Attachments at any level

E.

Operation resources. Including alternate resources

Full Access
Question # 9

The pick release of a project work order creates movement requests with the project and the task from the work order.

Which statement is NOT true about this?

A.

The expenditure type, expenditure date, and expenditure organization are derived when the work-ln-process material issue or work-in-process material pick transactions are interfaced to Costing.

B.

The expenditure type for the item is derived based on the Default Expenditure Type attribute in Inventory Management. The picks for the work order ore grouped by project costing, project, and task using pick slip grouping rules.

C.

The expenditure type and the expenditure organization from the work order are referenced onto the shop floor movement requests.

D.

The expenditure type and the expenditure organization from the work order are not referenced onto the shop floor movement requests.

Full Access
Question # 10

You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.

Which setup task must you perform to achieve this?

A.

Deselect the Count Point check box while defining the standard operation.

B.

Select the Automatically Transact check box while defining the standard operation.

C.

Select the Count Point check box while defining the standard operation.

D.

Ensure that the Charge Type of the resource is Automatic.

Full Access
Question # 11

Which three requirements are fulfilled by nonstandard work orders?

A.

Rescheduling

B.

Repair

C.

Rework

D.

Prototype

Full Access
Question # 12

A Production Operator needs to review the materials issued, resources charged, and operations performed for a job that was executed in the previous shift.

Which task should the operator select to review all the transactions in a single place for both work order and orderless execution?

A.

Report Resource, Material, and Operation Transactions

B.

Manage Work Orders

C.

Review Production Transaction History

D.

Review Dispatch List

Full Access
Question # 13

In a Manufacturing Cloud implementation, users are finding it difficult to track information about work orders executed across various work centers.

Which three information types in the Work Order Traveler can help users in this situation?

A.

Reservation against sales orders

B.

Hard pegging of items

C.

Item on-hand quantity

D.

Work definition details

E.

Product serial Information

Full Access
Question # 14

Which three can you set as Overcompletion Tolerance Type and its value for a subcomponent yield, so that the job order can report the excess production completion?

A.

Overcompletion Tolerance Type = Percentage; value = 0

B.

Overcompletion Tolerance Type = Percentage; value = 100

C.

Overcompletion Tolerance Type = Amount; value = 0

D.

Overcompletion Tolerance Type = Amount; value > 0

E.

Overcompletion Tolerance Type = Percentage; value > 0

Full Access
Question # 15

Your client needs to implement operational checks for compliance with training and job requirements. Which four statements are true about this functionality?

A.

A qualified operator need not be specified to report resource transactions.

B.

You have the ability to associate a Job profile with a Work definition operation resource.

C.

The qualification Is enforced during reporting of labor usage.

D.

You have the ability to associate a Job profile with a Standard operation resource.

E.

You do not have the ability to associate a Job profile with a Work order operation resource.

F.

The qualification Is used to warn a production supervisor If they assign operators that don't meet the skill requirements against the resource.

Full Access