You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)
While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify thereasonwhy the project transaction controls are notapplied. (Choose the best answer.)
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)
Which three are valid password complexity criteria while setting up password policies? (Choose three.)
Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?
(Choose two.)
You are currently involved in the implementation of the Project Financial Management solution for your client organization. Your client organization has two main lines of business: Consulting and Support. Consulting Services and Support Services organizations have different project planning, management, analysis and reporting requirements for the projects that they manage, though the management reporting and transaction processing requirements are the same for both the organizations.
What will be your recommendation?
Which product offering enables you to collaboratively plan and deliver projects by leveraging intuitive and integrated scheduling tools?
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met forexporting milestone tasks.(Choose three.)
Your organization has been awarded a new contract based on which you are allowed to sell:
Items not tracked in inventory
Inventory items
Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)
Which precedence order is used by the system for labor schedules to distribute payroll cost?
Which three tasks can be performed using the project requirements work area? (Choose three.)
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified thattheir cost spread distribution factor on a 10 spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two)
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?
You want tocreate a few project roles so as to restrict accessin the Project Financial Management work area to only the specific projects in which an employee is assigned as a team member. What are the two default project roles available to meet this requirement? (Choose two.)
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
What is the reason for this problem?
Which application would you use to map application roles to external roles? (Choose the best answer.)
Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
Stigma Consulting wants to implement the program management capability to coordinate and track their strategic programs.
Which three components are required to configure the program options as part of implementing the program management capability? (Choose three.)
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
Whichthreesetups can be configured by using Rapid Implementation for Project Financial Management Applications?
You havedefined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
Your organization has a requirement to create and apply a new theme for the application user interface.
Which option allows you to achieve this requirement?
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?