Question # 4

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

A.

USD 184

B.

USD 120

C.

USD 134

D.

USD 70

Full Access
Question # 5

As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)

A.

Pool Membership

B.

attributes that the project enterprise resources are assigned after creation

C.

Jobs

D.

Person Type

Full Access
Question # 6

While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)

A.

project classification

B.

project type

C.

project unit

D.

project organization

Full Access
Question # 7

You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify thereasonwhy the project transaction controls are notapplied. (Choose the best answer.)

A.

There is no expenditure type information available on the distribution set line.

B.

There is no expenditure organization information available on the distribution set line.

C.

There is noexpenditure item dateinformation available on the distribution set line.

D.

The account code combination is not available on the distribution set line.

Full Access
Question # 8

You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

A.

On Hold > Pending Acceptance > Active

B.

On Hold > Pending Approval > Active

C.

Pending Approval > Pending Acceptance > Active

D.

Pending Acceptance > Pending Approval > Active

Full Access
Question # 9

Which three are valid password complexity criteria while setting up password policies? (Choose three.)

A.

Complex: At least 8 characters, 1 uppercase, and 1 number

B.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters

C.

Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character

D.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character

E.

Simple: At least 8 characters and 1 number

Full Access
Question # 10

Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?

(Choose two.)

A.

Expenditure Type

B.

Task

C.

Top resource

D.

Expenditure Category

E.

Project

Full Access
Question # 11

You are currently involved in the implementation of the Project Financial Management solution for your client organization. Your client organization has two main lines of business: Consulting and Support. Consulting Services and Support Services organizations have different project planning, management, analysis and reporting requirements for the projects that they manage, though the management reporting and transaction processing requirements are the same for both the organizations.

What will be your recommendation?

A.

Define One Business Unit and Two Project Units

B.

Define Two Business Units and Two Project Units

C.

Define One Business Unit and Three Project Units

D.

Define Two Business Units and One Project Unit

Full Access
Question # 12

Which product offering enables you to collaboratively plan and deliver projects by leveraging intuitive and integrated scheduling tools?

A.

Resource Management

B.

Project Control

C.

Project Management

D.

Project Costing

Full Access
Question # 13

You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met forexporting milestone tasks.(Choose three.)

A.

only one labor resource assignment with 100 effort

B.

lowest-level tasks set up with non-zero duration

C.

lowest-level tasks set up with zero duration

D.

only one labor resource assignment with 0 effort

E.

percent work complete values of 0 or 100 percent

Full Access
Question # 14

Your organization has been awarded a new contract based on which you are allowed to sell:

    Items not tracked in inventory

    Inventory items

    Services

Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)

A.

Create two contract lines with a line type each of “free-form, project-based buy agreement” and “bundle sell, project-based”.

B.

Create two contract lines with a line type each of “sell intent, free-form, project-based” and “sell intent, item, project-based”.

C.

Create two contract lines with a line type each of “product, project-based, sell agreement, standalone” and “sell intent, item, project-based”.

D.

Create two contract lines with a line type each of “sell intent, item, project-based’ and “subscription, project-based, sell”.

Full Access
Question # 15

Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.

Identify the correct statement about the RBS and new resources. (Choose the best answer.)

A.

If the “Allow resource changes at project level” option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.

B.

If the “Allow resource changes at project level” option is set toNofor the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.

C.

If the “Allow resource changes at project level” option is set to Yes for the RBS, the new resources are available automatically at project level.

D.

If the “Allow resource changes at project level” option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.

Full Access
Question # 16

Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)

A.

If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.

B.

If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.

C.

If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.

D.

If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with thelowest number at the lowest level.

Full Access
Question # 17

Which precedence order is used by the system for labor schedules to distribute payroll cost?

A.

Element > Assignment Element > Assignment

B.

Assignment > Assignment Element > Element

C.

Assignment > Element > Assignment Element

D.

Assignment Element > Element > Assignment

Full Access
Question # 18

Which three tasks can be performed using the project requirements work area? (Choose three.)

A.

creating projects and tasks in the context of backlog items.

B.

creating issues for the backlog items.

C.

adding scrum master to backlog items.

D.

tracking backlog item status from the requirement storyboard.

E.

creating change orders for the backlog items.

Full Access
Question # 19

Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified thattheir cost spread distribution factor on a 10 spread point scale resembles:

0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two)

A.

Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.

B.

Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.

C.

Use the predefined Bell Curve spread with small deviations on the spread points.

D.

Use the predefined S-Curve spread with small deviations on the spread points.

Full Access
Question # 20

Your customer has the following setups on the project plan type that they are using for their projects:

Use Task Planned Dates as Task Assignment Dates = Yes

Automatically Roll Up Task Planned Dates = Yes

Synchronize Task Transaction Dates with Planned Dates = No

With these setups in place, you perform the following actions:

1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.

2. Create another new subtask (Sub Task 2) after the previous action is saved.

What would the correct behavior of the application be after these actions? (Choose the best answer.)

A.

After the creation of Sub Task 1, Project Start Date would remain unchanged as 01-Jul-2016 and Sub Task 2 would be created with 15-Jun-2016.

B.

After the creation and saving of Sub Task 1, Task Start Date would be changed to 01-Jul-2016 and Sub Task 2 would be created with 01-Jul-2016.

C.

After the creation of Sub Task 1, Project Start Date would be changed to 15-Jun-2016 and Sub Task 2 would be created with 15-Jun-2016.

D.

Project Start Date would remain unchanged as 01-Jul-2016 for both actions but the start dates on both subtasks would remain 15-Jun-2016.

Full Access
Question # 21

Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?

A.

Enterprise Contract Management

B.

Project Billing

C.

Project Control

D.

Project Costing

Full Access
Question # 22

You want tocreate a few project roles so as to restrict accessin the Project Financial Management work area to only the specific projects in which an employee is assigned as a team member. What are the two default project roles available to meet this requirement? (Choose two.)

A.

Project Executive- Security based on Project Hierarchy

B.

Project Accountant- Security based on BU for Assets, Expenditure BU for Costs and Contract BU for Revenue

C.

Project Manager- Security based on Project Assignment

D.

Project Billing Specialist- Security based on Contract BU

E.

Project Team Member- Security based on Project Assignment

Full Access
Question # 23

Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.

What are three conditions for new employees to show up in the list? (Choose three.)

A.

Current date is before the effective date of the resource, and you did not enable the “Include people with future-dated effective start dates” option during the search.

B.

All new employees created as persons must have an active supervisor.

C.

All new employees created as personsmust be assigned to a department.

D.

All new employees created as personsmust have an active assignment.

E.

All new employees created as persons must have an active project role.

Full Access
Question # 24

Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)

A.

Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.

B.

Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.

C.

Labor Demand FTE is calculated as Project Allocation hours divided by Project FTEhours, if project duration is used as the basis for viewing labor demand.

D.

Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.

Full Access
Question # 25

Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)

A.

Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule

B.

Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate

C.

Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule

D.

Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule

E.

Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule

Full Access
Question # 26

Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.

Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)

A.

assignment to one set only with common values

B.

assignment to one set only; no common values allowed

C.

assignment to multiple sets; common values allowed

D.

assignment to multiple sets; no common values allowed

Full Access
Question # 27

As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.

What is the reason for this problem?

A.

Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.

B.

Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.

C.

You can enable automatic reprocessing of expenditure items processed before the burden schedule change.

D.

All expenditure items charged to the task use the new burden schedule.

Full Access
Question # 28

Which application would you use to map application roles to external roles? (Choose the best answer.)

A.

Oracle Identify Manager

B.

Authorization Policy Manager

C.

BPM Work List

D.

Security Console

Full Access
Question # 29

Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)

A.

Project Contract-based costing

B.

Project Contract-based billing

C.

Project Contract Collection Center

D.

Contract Team Connect

Full Access
Question # 30

You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)

A.

Exceptions

B.

Accounting Calendar

C.

Workday Patterns

D.

Time Off

E.

Expenditure Type

Full Access
Question # 31

Stigma Consulting wants to implement the program management capability to coordinate and track their strategic programs.

Which three components are required to configure the program options as part of implementing the program management capability? (Choose three.)

A.

Calendar

B.

Calculation Methods

C.

Derivation Methods

D.

Currencies

E.

Accounting Methods

Full Access
Question # 32

Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)

A.

Receipt Accounting

B.

Payables

C.

Fixed Asset

D.

Purchasing

Full Access
Question # 33

Whichthreesetups can be configured by using Rapid Implementation for Project Financial Management Applications?

A.

Expenditure Types

B.

Project Templates

C.

Work Type

D.

Project Types

E.

Project Class Categories

Full Access
Question # 34

You havedefined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)

A.

The two expenditure types are not assigned to the reference data set that is assigned to theproject unitin which the transaction is performed.

B.

The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.

C.

The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.

D.

The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.

Full Access
Question # 35

Your organization has a requirement to create and apply a new theme for the application user interface.

Which option allows you to achieve this requirement?

A.

Structure Page

B.

Appearance Page

C.

Setup and Maintenance Work Area

D.

User Interface Text

Full Access
Question # 36

You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

A.

1000

B.

900

C.

800

D.

600

Full Access
Question # 37

You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?

A.

Assign tasks to various users who are responsible for managing setup data.

B.

Monitor the progress of completing setup tasks.

C.

Select the offering you want to implement.

D.

Generate a list of setup tasks.

E.

Enable optional functional areas and features by opting in.

Full Access