Explanation
This question mentions about specification in construction. In this sector, specifications are written documents that describe the materials and workmanship required for a development. They do not include cost, quantity or drawn information and need to be read alongside other contract documentation such as quantities, schedules and drawings.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further development by a contractor or supplier, to prescriptive (closed) specifications for which the design is already complete when the project is tendered.
Prescriptive specifications typically contain detailed descriptions of the following components:
- General requirements relating to regulations and standards.
- The type of products and materials required.
- The execution and installation methods required.
Prescriptive specifications give the client much more certainty about the end product when making investment decisions (such as when they appoint the contractor), and place a greater burden on the designer to ensure proper installation rather than the contractor.
[Reference:, - CIPS study guide page 116-120, - Prescriptive specification - Designing Buildings Wiki, LO 3, AC 3.1]